Big Blue
The project would improve stand conditions by commercially thinning and group select harvesting 35-to 80-year-old timber stands in the Upper Blue River sub-watershed. Road maintainenance, restoration, and decommissioning would also occur.
Location Summary
The project area is represented by the Upper Blue River subwatershed, and is located approximately 4 miles northeast of the Blue River Community.
District: McKenzie River Ranger District
Project Milestones
Milestone | Date |
---|---|
Scoping Start | 12/15/2008 |
Comment Period | 06/15/2009 |
Objection Period Start | N/A |
Decision | 07/23/2009 |
Implementation | 04/01/2010 (Estimated) |
Project Documents
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public