Elk Late-Successional Reserve Enhancement Project
Reduce tree densities and fuel loads with thinning and fuels treatments on approximately 3,420 acres in the Elk Flat Late-Successional Reserve and adjacent matrix lands to protect current late/mid-successional habitat and develop future late-successional habitat conditions. Meadow conditions in Elk Flat outside of the LSR will also be restored. Access Google Earth files for this project.
Location Summary
North of Pilgrim Creek Snowpark adjacent to Elk Flat. MA 2 and 3. MP VII (LSR)/IX (RR)/VIII (Matrix)
District: McCloud Ranger District
Project Milestones
Milestone | Date |
---|---|
NOI in Federal Register | 02/28/2013 |
DEIS NOA in Federal Register | 01/15/2016 |
FEIS NOA in Federal Register | 04/18/2016 |
Objection Period Start | 04/22/2016 |
Decision | 07/21/2016 |
Implementation | 09/01/2016 (Estimated) |
Project Documents
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public