Glacier Ditch Piping

MFID proposes to install 500 of 18-inch HDPE pipe in the upper Glacier ditch on National Forest Lands. This is part of a larger project that will pipe approximately 10,000 feet of Glacier ditch.

Project Information

Expected Analysis Type
Decision Memo

Categorical Exclusion
Approval, modification, or continuation of minor special uses of National Forest System lands that require less than five contiguous acres of land.

Special Authority
Not applicable / Other

Lead Management Unit
Hood River Ranger District

Notice and Comment Regulation
Not Subject to Regulations

Project Purpose
Special use management; Facility management

Project Activity
Facility maintenance; Watershed improvements

Project Status

Current Status
Analysis Completed

Project Decision Information

Glacier Ditch Piping Decision Memo

Decision Signed Date
2011-05-06

Last Updated: 05/06/2011

https://www.fs.usda.gov/project/?project=32472&exp=detail