Glacier Ditch Piping
MFID proposes to install 500 of 18-inch HDPE pipe in the upper Glacier ditch on National Forest Lands. This is part of a larger project that will pipe approximately 10,000 feet of Glacier ditch.
Project Information
Expected Analysis Type
Decision Memo
Categorical Exclusion
Approval, modification, or continuation of minor special uses of National Forest System lands that require less than five contiguous acres of land.
Special Authority
Not applicable / Other
Lead Management Unit
Hood River Ranger District
Notice and Comment Regulation
Not Subject to Regulations
Project Purpose
Special use management; Facility management
Project Activity
Facility maintenance; Watershed improvements
Project Status
Current Status
Analysis Completed
Project Decision Information
Glacier Ditch Piping Decision Memo
Decision Signed Date
2011-05-06