Kruzof Island Outfitter Guide EA
To determine the amount of recreation use that the Mud Bay and Eagle River road systems can accommodate, and then decide how much should be allocated to commercial use.
Location Summary
Mud Bay Road System and Eagle River Road System, Kruzof Island
District: Sitka Ranger District
Project Milestones
Milestone | Date |
---|---|
Scoping Start | 08/28/2013 |
Comment Period | 10/31/2013 |
Objection Period Start | 02/23/2015 |
Decision | 04/21/2015 |
Implementation | 04/01/2015 (Estimated) |
Project Documents
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public