PacifiCorp Special Use Permit Renewal

Renewal of a permit for an existing distribution feeder line and single phase distribution line for a 50 year term. There will be no ground disturbance associated with this renewal.

Location Summary

The distribution line runs from Prospect approximately 13 miles along Highway 62 to Union Creek.

District: High Cascades Ranger District

Project Milestones

MilestoneDate
Scoping Start05/06/2013
Comment Period09/16/2013
Objection Period StartN/A
Decision10/31/2013
Implementation11/01/2013 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public