Glacier Electric Cooperative Shed 7 buried line

Glacier electric cooperative wants to bury an existing overhead electric line that is in an avalanche run-out zone near Burlington Northern Santa Fe railroad snowshed 7. The buried line will be 550 ft. from existing utility corridor.

Location Summary

The project is located in the railroad right of way in John F. Stevens canyon near BNSF snowshed 7.

District: Hungry Horse Ranger District

Project Milestones

MilestoneDate
Scoping Start10/15/2019
Comment PeriodN/A
Objection Period StartN/A
Decision11/18/2020
Implementation05/2021 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public