Boise River Basin Feasibility Study

Bureau of Reclamation has completed a Draft EIS for the Boise River Basin Feasibility Study. The USFS is a cooperating agency. To accomplish this project the USFS would need to modify a Forest Roads and Trails Act Easement. Bureau of Reclamation is pausing the NEPA process until further design can be conducted to help inform elements of the proposed action. The project is anticipated to be paused until the later part of 2022.

Location Summary

Anderson Ranch Reservoir, 28 miles northeast of Mountain Home, Idaho.

District: Mountain Home Ranger District

Project Milestones

MilestoneDate
NOI in Federal Register08/09/2019
DEIS NOA in Federal Register07/31/2020
FEIS NOA in Federal Register10/2024 (Estimated)
Objection Period Start04/2024 (Estimated)
Decision12/2024 (Estimated)
Implementation06/2025 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public