Skyline Mine Little Eccles Tract Environmental Impact Statement

The complete Environmental Impact Statement for the Little Eccles Mine Expansion is now available on BLM's ePlanning site found here: https://eplanning.blm.gov/eplanning-ui/project/2015277/510.

Location Summary

1 mile west of Electric Lake

District: Ferron Ranger District

Project Milestones

MilestoneDate
NOI in Federal Register04/15/2024
DEIS NOA in Federal RegisterN/A
FEIS NOA in Federal RegisterN/A
Objection Period StartN/A
Decision08/2025 (Estimated)
Implementation10/2025 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public