Forest Road 164 Reconstruction
The 11.6-mile-long project area will be cleared and grubbed within 16 feet of the road centerline or as needed to create ditching. All cross-drain culverts will be replaced with polymer coated arch pipes. The entire road length will be resurfaced.
Location Summary
Forest Road 164 between County Highway GG and Forest Road 163.
District: Great Divide Ranger District
Project Milestones
Milestone | Date |
---|---|
Scoping Start | 01/31/2022 |
Comment Period | 08/28/2025 |
Objection Period Start | 08/28/2025 |
Decision | 11/2025 (Estimated) |
Implementation | 11/2025 (Estimated) |
Project Documents
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public