Cross-Tie 500-kV Transmission Project

Construction, operation, maintenance and decommissioning of a 500kV transmission line between Clover Substation in Juab County, Utah, and Robinson Summit Substation in White Pine County,Nevada

Location Summary

The Project is located in Beaver, Juab, and Millard Counties, Utah, and White Pine County, Nevada.

District: Ely Ranger District

Project Milestones

MilestoneDate
NOI in Federal Register05/02/2022
DEIS NOA in Federal Register11/09/2023
FEIS NOA in Federal Register09/20/2024
Objection Period Start09/21/2024
Decision09/2025 (Estimated)
Implementation09/2025 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public