White Oak Mountain Entergy Electric Line Relocation Project

The Big Piney Ranger District is considering a proposal from Entergy Electric Company to relocate approximately 3.7 miles of electric line serving White Oak Mountain. The location is less than a mile northeast of Hector, AR.

Location Summary

This project is approximately a mile north of the community of Hector, AR.

District: Bayou Ranger District

Project Milestones

MilestoneDate
Scoping Start11/28/2023
Comment PeriodN/A
Objection Period StartN/A
Decision06/04/2024
Implementation08/2024 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public