Sierra Pacific Power Company (NV Energy) Powerline Rebuild Project - Lines 101, 102, 133

NV Energy proposes replacement of three electrical transmission lines (101, 102, and 133) with modernized electrical design line, using existing alignment (right of way) to significantly improve reliability within the electric power grid.

Location Summary

Truckee Ranger District of the Tahoe National Forest and the Carson District of the Humbolt Toiyabe National Forest.

Forests: Carson Ranger District, Truckee Ranger District

Project Milestones

MilestoneDate
Scoping Start07/01/2024
Comment PeriodN/A
Objection Period StartN/A
Decision10/2025 (Estimated)
Implementation10/2025 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public