Forest Wide Thinning & Potential Control Line Treatments

Project will analyze forest plantations less than 80 years of age for commercial thinning and risk reduction treatments along identified Potential Control Lines (PCL). Storymap: https://storymaps.arcgis.com/stories/9b4427f943764a85a8661f8dab1576a6

Location Summary

Gifford Pinchot National Forest lands where applicable.

District: Gifford Pinchot National Forest All Units

Project Milestones

MilestoneDate
Scoping Start07/01/2024
Comment Period04/12/2025
Objection Period Start07/03/2025
Decision10/09/2025
Implementation11/2025 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public