2025 Troy Cablevision Fiber Project

The proposal is for the placement of buried conduit within existing rights-of-way on ~6 acres, containing either a 144 or 288 count fiber optic cable via plow and directional bore at a depth of 36 inches with handhole placements every 1500 feet.

Location Summary

Alabama Highway 55 and Alabama Highway 29 within existing Right of Way (ROW)

Districts: Conecuh Ranger District, Tuskegee Ranger District

Project Milestones

MilestoneDate
Scoping Start02/07/2025
Comment Period03/11/2025
Objection Period StartN/A
Decision04/03/2025
Implementation04/2025 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public