NM Gas Company Hwy 518 Pipeline

The FS has recieved a proposal to install a buried 4-inch diameter natural gas distribution pipeline adjacent to highway 518 from Talpa to Pot Creek and would require the Forest to issue a new Special Use Authorization for construction & maintenance

Location Summary

The proposed pipeline would begin in Talpa at the junction highway 518 and Forest Road 437 and continue south on highway 518 to a point adjacent to the Southern Methodist University.

District: Camino Real Ranger District

Project Milestones

MilestoneDate
Scoping Start05/13/2025
Comment PeriodN/A
Objection Period StartN/A
Decision08/04/2025
Implementation10/2025 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public