State: Montana | | | | | | | | | | | |
Timber Volumes Planned for Offer within Inventoried Roadless Areas (IRAs). Note: Total Timber Volume includes salvage and biomass. | | |
The following table summarizes, by fiscal year TIMBER VOLUMES PLANNED FOR OFFER within Inventoried Roadless Areas. The following abbreviations are used: FY = Fiscal Year, MMBF = Million Board Feet | | List total planned MMBF and road miles for unroaded and roaded portions of IRAs | | Planned offer in unroaded portion of IRA that does not require road construction or reconstruction by sale type and logging system |
Timber Harvest Volume | FY '00 | FY '01 | FY '02 | FY '03 | FY '04 | Total Planned thru FY '04 | Possible Reduction thru FY '04 | Total Road Mileage | | Unroaded IRA portion totals | Roaded IRA portion totals | | | Stewardship sale MMBF | Commodity sale MMBF | Sub total MMBF |
MONTANA | | | |
Total planned offered within IRAs MMBF | 4.21 | 7.77 | 4.37 | 0.37 | 0.37 | 17.09 | | | | 6.20 | 10.89 | | Helicopter | 3.90 | 0.00 | 3.90 |
Of the above, how much requires road (re)construction (MMBF)? | 0.10 | 2.90 | 0.80 | 0.00 | 0.00 | | 3.80 | | | 2.30 | 1.50 | | Cable logging system | 0.00 | 0.00 | 0.00 |
How many miles of classified road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Ground based logging | 0.00 | 0.00 | 0.00 |
How many miles of classified road must be reconstructed? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Total MMBF | 3.90 | 0.00 | 3.90 |
How many miles of temporary road construction will be required? | 1.25 | 3.70 | 0.30 | 0.00 | 0.00 | | | 5.25 | | 1.50 | 3.75 | | |
LEWIS & CLARK | | | |
Total planned offered within IRAs MMBF | 1.30 | 0.00 | 0.00 | 0.00 | 0.00 | 1.30 | | | | 0.00 | 1.30 | | Helicopter | 0.00 | 0.00 | 0.00 |
Of the above, how much requires road (re)construction (MMBF)? | 0.10 | 0.00 | 0.00 | 0.00 | 0.00 | | 0.10 | | | 0.00 | 0.10 | | Cable logging system | 0.00 | 0.00 | 0.00 |
How many miles of classified road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Ground based logging | 0.00 | 0.00 | 0.00 |
How many miles of classified road must be reconstructed? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Total MMBF | 0.00 | 0.00 | 0.00 |
How many miles of temporary road construction will be required? | 1.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 1.00 | | 0.00 | 1.00 | | |
CUSTER | | | |
Total planned offered within IRAs MMBF | 0.37 | 0.37 | 0.37 | 0.37 | 0.37 | 1.85 | | | | 0.00 | 1.85 | | Helicopter | 0.00 | 0.00 | 0.00 |
Of the above, how much requires road (re)construction (MMBF)? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | 0.00 | | | 0.00 | 0.00 | | Cable logging system | 0.00 | 0.00 | 0.00 |
How many miles of classified road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Ground based logging | 0.00 | 0.00 | 0.00 |
How many miles of classified road must be reconstructed? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Total MMBF | 0.00 | 0.00 | 0.00 |
How many miles of temporary road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | |
BITTERROOT | | | | | |
Total planned offered within IRAs MMBF | 0.00 | 0.00 | 2.00 | 0.00 | 0.00 | 2.00 | | | | 0.00 | 2.00 | | Helicopter | 0.00 | 0.00 | 0.00 |
Of the above, how much requires road (re)construction (MMBF)? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | 0.00 | | | 0.00 | 0.00 | | Cable logging system | 0.00 | 0.00 | 0.00 |
How many miles of classified road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Ground based logging | 0.00 | 0.00 | 0.00 |
How many miles of classified road must be reconstructed? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Total MMBF | 0.00 | 0.00 | 0.00 |
How many miles of temporary road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | |
FLATHEAD | |
Total planned offered within IRAs MMBF | 1.44 | 0.00 | 0.00 | 0.00 | 0.00 | 1.44 | | | | 0.00 | 1.44 | | Helicopter | 0.00 | 0.00 | 0.00 |
Of the above, how much requires road (re)construction (MMBF)? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | 0.00 | | | 0.00 | 0.00 | | Cable logging system | 0.00 | 0.00 | 0.00 |
How many miles of classified road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Ground based logging | 0.00 | 0.00 | 0.00 |
How many miles of classified road must be reconstructed? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Total MMBF | 0.00 | 0.00 | 0.00 |
How many miles of temporary road construction will be required? | 0.25 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.25 | | 0.00 | 0.25 | | |
HELENA | |
Total planned offered within IRAs MMBF | 0.00 | 5.80 | 2.00 | 0.00 | 0.00 | 7.80 | | | | 3.50 | 4.30 | | Helicopter | 1.20 | 0.00 | 1.20 |
Of the above, how much requires road (re)construction (MMBF)? | 0.00 | 2.90 | 0.80 | 0.00 | 0.00 | | 3.70 | | | 2.30 | 1.40 | | Cable logging system | 0.00 | 0.00 | 0.00 |
How many miles of classified road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Ground based logging | 0.00 | 0.00 | 0.00 |
How many miles of classified road must be reconstructed? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Total MMBF | 1.20 | 0.00 | 1.20 |
How many miles of temporary road construction will be required? | 0.00 | 3.70 | 0.30 | 0.00 | 0.00 | | | 4.00 | | 1.50 | 2.50 | | |
IDAHO PANHANDLE | |
Total planned offered within IRAs MMBF | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | | 0.00 | 0.00 | | Helicopter | 0.00 | 0.00 | 0.00 |
Of the above, how much requires road (re)construction (MMBF)? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | 0.00 | | | 0.00 | 0.00 | | Cable logging system | 0.00 | 0.00 | 0.00 |
How many miles of classified road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Ground based logging | 0.00 | 0.00 | 0.00 |
How many miles of classified road must be reconstructed? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Total MMBF | 0.00 | 0.00 | 0.00 |
How many miles of temporary road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | |
KOOTENAI | |
Total planned offered within IRAs MMBF | 1.10 | 0.00 | 0.00 | 0.00 | 0.00 | 1.10 | | | | 1.10 | 0.00 | | Helicopter | 1.10 | 0.00 | 1.10 |
Of the above, how much requires road (re)construction (MMBF)? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | 0.00 | | | 0.00 | 0.00 | | Cable logging system | 0.00 | 0.00 | 0.00 |
How many miles of classified road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Ground based logging | 0.00 | 0.00 | 0.00 |
How many miles of classified road must be reconstructed? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Total MMBF | 1.10 | 0.00 | 1.10 |
How many miles of temporary road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | |
LOLO | |
Total planned offered within IRAs MMBF | 0.00 | 1.60 | 0.00 | 0.00 | 0.00 | 1.60 | | | | 1.60 | 0.00 | | Helicopter | 1.60 | 0.00 | 1.60 |
Of the above, how much requires road (re)construction (MMBF)? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | 0.00 | | | 0.00 | 0.00 | | Cable logging system | 0.00 | 0.00 | 0.00 |
How many miles of classified road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Ground based logging | 0.00 | 0.00 | 0.00 |
How many miles of classified road must be reconstructed? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Total MMBF | 1.60 | 0.00 | 1.60 |
How many miles of temporary road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | |
|
| | | | | | | | | | | | | | | | |