Timber Volumes Planned for Offer within Inventoried Roadless Areas (IRAs). Note: Total Timber Volume includes salvage and biomass. | | |
The following table summarizes, by fiscal year TIMBER VOLUMES PLANNED FOR OFFER within Inventoried Roadless Areas. The following abbreviations are used: FY = Fiscal Year, MMBF = Million Board Feet | | List total planned MMBF and road miles for unroaded and roaded portions of IRAs | | Planned offer in unroaded portion of IRA that does not require road construction or reconstruction by sale type and logging system |
Timber Harvest Volume | FY '00 | FY '01 | FY '02 | FY '03 | FY '04 | Total Planned thru FY '04 | Possible Reduction thru FY '04 | Total Road Mileage | | Unroaded IRA portion totals | Roaded IRA portion totals | | | Stewardship sale MMBF | Commodity sale MMBF | Sub total MMBF |
TENNESSEE | | | |
Total planned offered within IRAs MMBF | 0.00 | 1.60 | 0.00 | 0.00 | 0.00 | 1.60 | | | | 1.60 | 0.00 | | Helicopter | 0.00 | 0.00 | 0.00 |
Of the above, how much requires road (re)construction (MMBF)? | 0.00 | 0.40 | 0.00 | 0.00 | 0.00 | | 0.40 | | | 0.40 | 0.00 | | Cable logging system | 0.00 | 0.00 | 0.00 |
How many miles of classified road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Ground based logging | 1.20 | 0.00 | 1.20 |
How many miles of classified road must be reconstructed? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Total MMBF | 1.20 | 0.00 | 1.20 |
How many miles of temporary road construction will be required? | 0.00 | 1.35 | 0.00 | 0.00 | 0.00 | | | 1.35 | | 1.35 | 0.00 | | |
CHEROKEE | | | |
Total planned offered within IRAs MMBF | 0.00 | 1.60 | 0.00 | 0.00 | 0.00 | 1.60 | | | | 1.60 | 0.00 | | Helicopter | 0.00 | 0.00 | 0.00 |
Of the above, how much requires road (re)construction (MMBF)? | 0.00 | 0.40 | 0.00 | 0.00 | 0.00 | | 0.40 | | | 0.40 | 0.00 | | Cable logging system | 0.00 | 0.00 | 0.00 |
How many miles of classified road construction will be required? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Ground based logging | 1.20 | 0.00 | 1.20 |
How many miles of classified road must be reconstructed? | 0.00 | 0.00 | 0.00 | 0.00 | 0.00 | | | 0.00 | | 0.00 | 0.00 | | Total MMBF | 1.20 | 0.00 | 1.20 |
How many miles of temporary road construction will be required? | 0.00 | 1.35 | 0.00 | 0.00 | 0.00 | | | 1.35 | | 1.35 | 0.00 | | |
| | |
| | | | | | | | | | | | | | | | |