Case Study Contributors
Location
Tributary to Pacific Ocean, Northern California, USA. MAP
Project Type
Pre-Project Conditions
Pre-Project Barrier
Hydrologic Characteristics
Ecological Value
Project Characteristics
Challenges and Lessons Learned
Project Lead
Mendocino County Department of Transportation
Project Funding
Total Project Cost
| Construction | $ | 93,204 |
| Materials | $ | 91,535 |
| Engineering | $ | 44,218 |
| Easements | $ | 5,489 |
| Planning | $ | 2,981 |
| Total | $ | 237,427 |
Completion Date
October 2003
Project Description
The existing CSP pipe arch was undersized and in poor condition. The 3 ft (0.9 m) perched outlet, along with an inadequate jump pool, created a barrier to all age classes of coho, steelhead, and resident trout. Currently, the State Highway culvert 500 ft (152 m) upstream is blocking passage to 2.3 miles (6 km) of upstream habitat.
The replacement structure is a roughened channel inside a pre-fabricated concrete arch culvert set on cast-in-place footings. The footings were installed level, 4 ft (1.2 m) below grade with angular rock lining the footings to prevent scour.
The streambed through the culvert was constructed from a mix of angular cobble to small boulders to provide sufficient roughness and maintain the relatively steep channel grade. To prevent subsurface flow through the larger material, fine material (sand and silt) was mixed and jetted into the bed. The upper 40 ft (12 m) of the channel bed inside the culvert was constructed at a 1.2% slope, while the lower 20 ft (6 m) is oversteepened at 8.8%. The upstream channel was expected to incise 2 ft (0.6 m) and release fine sediments, exposing spawning gravels.
The aesthetic treatment required by adjacent land owner included the use of stamped concrete wing walls resembling cobblestone and replanting the site with non-native vegetation.
Post Project Observations and Lessons Learned
Monitoring in 2004 and 2005 found the new crossing to be a significant improvement in both fish passage and storm flow conveyance. Since construction, headcutting exposed bedrock 30 ft (9 m) upstream of the crossing, preventing additional upstream incision. Longitudinal profiles of the culvert streambed showed the slope through the steeper section had decreased and the slope break had moved upstream. While it is much steeper than the adjacent channel, the roughness of the cobbles and small boulders may provide pathways of reduced velocities for fish to move through. Future adjustments to the channel bed will likely further decrease the slope.
Published 02/23/07