Case Study Contributors
Bob Gubernick , Engineering Geologist, Tongass National Forest
Location
Mitkof Island, Tongass National Forest, Southeast Alaska, USA. MAP
Project Type
Pre-Project Conditions
Pre-Project Barrier
Watershed Characteristics
Ecological Value
Provide access to 0.22 miles (0.35 km) of upstream spawning and rearing habitat for resident and anadromous Dolly Varden
Project Characteristics
Challenges
Project Contributors
Project Funding
US Forest Service
Completion Date
July 2002
Total Project Cost
Approximately $40,000
Project Description
The site was chosen for culvert replacement due to its proximity to Big Creek and the high quality spawning and rearing habitat utilized by both resident and anadromous Dolly Varden. The stream is high gradient, with an incised channel and step-pool morphology. Stream gradient is controlled by steps formed by bedrock, angular cobbles, and woody debris.
The replacement culvert is a 6.5 ft (2 m) diameter CMP at 4% slope and embedded 40% of its diameter. The culvert was backfilled with a streambed mixture composed of 60% USFS Class 4 rock mixture and 40% native streambed material. The Class 4 rock gradation is as follows:
% of rock
by weight Cubic dimensions
20 18 - 20 in (450 - 500 mm)
30 14 - 18 in (350 - 450 mm)
40 6 - 14 in (150 - 350 mm)
10 0 - 6 in (0 - 150 mm)
Because the material that forms steps in steep streams in infrequently mobile, the larger rock in the mixture was sized to be stable at the 50 year flow. The stability analysis was based on several equations that predict mobility as a function of rock size and average boundary shear stress.
When constructing steep streambeds it is important to include stable grade controlling features. The bed in the culvert was shaped to create a step-pool morphology with an average slope of 4%, similar to the adjacent channel. Steel bed retention sills 1.3 ft (0.4 m) tall were welded into the culvert every 10 ft (3 m) to buttress the steps and maintain bedform during high flows. Rocks larger than the D84 were used to construct rock steps, and placed along the culvert walls to create channel margins.
The bed material was placed in the culvert using a 3 sided box pushed along a steel I-beam by an excavator with a driveshaft from a log truck. This provided a 20 ft (6 m) reach into the culvert, requiring filling from both ends. About 33 ft (10 m) of channel below the crossing was regraded and two rock weirs were constructed for grade control.
The design and construction of this crossing is documented in more detail in an online presentation.
Post Project Observations
In the years following installation, anadromous adult Dolly Varden were observed upstream of the culvert, which was a complete barrier prior to the project.
Lessons Learned
Published 09/17/07