Fish Passage Case Studies

Tributary to Big Creek
40,000 Road, Mile Post 3.337

Step-Pool Stream Simulation with Bed Retention Sills

Case Study Contributors
Bob Gubernick , Engineering Geologist, Tongass National Forest

Location
Mitkof Island, Tongass National Forest, Southeast Alaska, USA. MAP

Project Type

  • Stream Simulation of Step Pool Channel
  • Embedded Culvert with Bed Retention Sills

Pre-Project Conditions

  • Corrugated metal pipe (CMP) with 5 ft (1.5 m) diameter at 3.2% slope
  • Poor culvert alignment with upstream channel
  • 1 ft (0.3 m) drop at outlet onto steep riprap

Pre-Project Barrier
Depth, velocity, and leap barrier to resident Dolly Varden

Watershed Characteristics

  • Drainage Area: 0.23 mi2 (0.6 km2)
  • 100-year Peak Flow: 122 cfs (3.5 cms)
  • 2-year Peak Flow: 55 cfs (1.56 cms)
  • High Fish Passage Design Flow: 22 cfs (0.62 cms)
  • Bankfull Channel Width: 9 ft (2.8 m)
  • Stream Channel Slope: 7%

Ecological Value
Provide access to 0.22 miles (0.35 km) of upstream spawning and rearing habitat for resident and anadromous Dolly Varden

Project Characteristics

  • New pipe-arch (squash pipe) culvert, 9.5 ft (2.9 m) span x 6.5 ft (2.0 m) rise,
  • Culvert placed at 7.7% slope (natural stream gradient) and embedded 2.0 ft (0.60 m)
  • Bed retention sills 1.1 ft (0.34 m) tall, spaced 11.5 ft (3.5 m) apart
  • Infill culvert with bed material to form steps
  • Boulder steps sized for stability up to 50-year peak flow, similar to stability of reference reach

Challenges

  • Simulating step-pool form and pattern in steep (7%) incised channel
  • Shallow bedrock (2-4 ft [0.6-1.2 m]) required use of a squash pipe which has a lower profile for given width over circular pipes
  • Preserving large spruce trees while forming upstream and downstream banks

Project Contributors

  • Tongass National Forest
  • Olsen Construction
  • Ketchikan Ready-Mix & Quarry
  • Chinook Engineering

Project Funding
US Forest Service

Completion Date
July 2002

Total Project Cost
Approximately $40,000

 


Project Description

The site was chosen for culvert replacement due to the quality and quantity of upstream spawning and rearing habitat for resident Dolly Varden and the crossing’s proximity to Big Creek, a high valued salmonid stream. The stream is a high gradient (7%), incised channel with step pool morphology. Water cascaded over riprap at the outlet, creating a fish passage barrier.

Due to shallow bedrock and a narrow bankfull width, a squash pipe, embedded 30% of its height, was selected for the replacement structure. Steel bed retention sills sized to be ½ the embedded depth were welded inside the culvert every 11.5 ft (3.5 m). These sills buttress the downstream side of each step to prevent loss of bedform structure during high flows. The culvert was backfilled with a mixture of 60% class 4 riprap, 40% native streambed material. Material was placed in the culvert using a steel I-beam as a track for a 3-sided box, which was filled with rock and then pushed by an excavator into the culvert with a logging truck driveline.

Stream channel immediately above and below the crossing was graded to conform to adjacent stream conditions and improve hydraulic alignment. The culvert alignment was adjusted in the field to protect a large spruce tree not shown on the design plans.

 

Culvert and Weir Dimensions
Total Length: 65.6 ft (20 m) Drop over step: 10 in (0.25 m)
Total drop: 5.05 ft (1.53 m) Rock size in steps: 1.5 ft (0.45 m)
Culvert dimensions: 9.5 ft span x 6.5 ft rise
(2.9 m x 2.0 m)
Embedded depth: 2 ft (0.62 m)
Bed retention
sill spacing:
11.5 ft (3.5 m) Bed retention
sill height:
1.1 ft (0.3m)
Length of channel re-grade: Downstream
33 ft (10.6 m)
Upstream 16.5 ft (5 m)
Culvert infill 60% class 4 riprap with
40% stream bed material

 

Class 4 Riprap Gradation
Percent of Mixture Diameter Mass
20% 450 - 500 mm (18 - 20 in) 250 - 350 kg (550 - 772 lb)
30% 350 - 450 mm (14 - 18 in)   100 - 250 kg (220 - 550 lb)
40% 150 - 350 mm (6 - 14 in) 10 -100 kg  (22 - 220 lb)
10% 0-150 mm  (0 - 14 in) 0 - 10 kg (0 - 22 lb)


The design and construction of this crossing is documented in more detail in an online presentation.

Material Sizing:
The channel slope provides a guide for the design of the step pools. With 11.5 ft (3.5 m) between steps, each step maintains a drop measured from crest to crest. Headwater at high flows was calculated assuming a Manning’s roughness coefficient (n) of 0.090 to account for bed roughness. This roughness corresponds with guidance provided by Oregon State University Forest Engineering Department for mountain stream containing similar sized material. Using the velocity versus stone weight hydraulic design chart in EM 1110-2-1601 yielded a stable rock size for the 50 year peak flow, which matched well with the rock size forming the steps in the reference reaches.

A similar project utilized an approach based on shear stress to size the stream simulation material.

Post Project Observations

The site experienced minor headcutting upstream that was stopped within 100 ft (30 m) of the culvert inlet by rock and log steps. Rock and sediment was deposited just downstream of the culvert behind a fallen log that causes backwater conditions. Initially left for habitat, this log has led to 0.5 - 1 ft (0.15 - 0.3 m) of aggradation below the outlet.

In the years following installation, the channel appears stable and anadromous adult Dolly Varden have been observed upstream of the culvert.

Lessons Learned

References
1. USACE EM 1110-2-1601, July 1991, USBR Nomograph Appendix 3 Plate 29
2. Oregon State University Forest Engineering Institute Notes, Vol. III, 1991


Published 09/18/07