Fish Passage Case Studies

Mynot Creek

Concrete Bottomless Arch Culvert with Regraded Channel and Sediment Removal

Location
Klamath River Basin, Northern California, USA. MAP

Project Type

  • Bottomless Arch Culvert
  • Stream Simulation Design

Pre-Project Conditions

  • Concrete Double Box Culvert: 24 ft (7.3 m) wide, 6.5 ft (2.0 m) high, and 42 ft (12.8 m) long
  • Undersized culvert, overtopped 10-year peak flow
  • Highly aggraded channel upstream of culvert

Pre-Project Barrier

  • Velocity, depth, and leap barrier
  • Complete barrier for all age classes of salmonids

Watershed Characteristics

  • Drainage Area: 3.13 mi2 (8.1 km2)
  • Average Channel Width: 25 - 30 ft (7.6 – 9.1 m)
  • 100-year Peak Flow: 2,643 cfs (75 cms)
  • 2-year Peak Flow: 648 cfs (18.3 cms)

Ecological Value

  • Provide access to 2.5 miles (4.0 km) of upstream spawning and rearing habitat for coho, chinook, steelhead, and cutthroat trout
  • Flush sediment from aggraded upstream channel to increase habitat complexity

Project Characteristics

  • Precast Concrete Arch: 28 ft (8.5 m) wide x 11 ft (3.4 m) high x 72 ft (21.9 m) long
  • Placement of ½ ton boulders inside culvert every 10 ft to create resting areas for juvenile salmonids
  • Regrade 1,100 ft (335 m) of aggraded channel and removal of 1,200 cy (920 m3) of sediment
  • 2 rock weirs installed upstream for grade control and 4 boulder instream habitat structures

Challenges

  • Protecting downstream restoration projects from sediment release
  • Estimating stable channel grade and volume of aggraded sediment to remove
  • Designing for skewed stream-road alignment
  • Transporting twelve 15 ton pre-fabricated concrete arches to site

Project Contributors

  • California Conservation Corps
  • Del Norte County Community Development Dept.
  • Randy Klein
  • Jeff Anderson & Associates

Project Funding

  • California Dept. of Fish and Game
  • US Fish and Wildlife
  • Del Norte County Community Development Dept.

Completion Date
October 2003

Project Cost

Construction $ 261,236
Materials $ 139,111
Engineering $ 40,704
Planning $ 715

Total $ 441,766

 


Project Description

The existing double box concrete culvert and outlet apron had a wide flat bottom that created both a water velocity and depth barrier to all adult and juvenile salmonids. The perched outlet apron also presented a leap barrier at migration flows. The undersized culvert, possibly combined with historic realignment and straightening of the channel, caused the upstream channel to aggrade more than 3 ft (0.9 m). This channel aggradation buried storm drains, decreased channel conveyance, and increased flooding of surrounding pastures and a local elementary school. This site received a priority ranking of 5th in the Del Norte County Inventory and Fish Passage Evaluation Report.

A 1,600 ft (490 m) longitudinal profile of the channel was surveyed to identify the stable channel grade and estimate the amount of stored sediment upstream of the culvert. Analysis of the profile indicated localized channel aggradation, as deep as 3 ft (0.9 m), present at the culvert inlet and extending approximately 800 ft (244 m) upstream. The aggradation is partially attributed to frequent ponding of floodwaters at the undersized culvert inlet. In this reach the channel grade was uncharacteristically low and severely lacked complexity, such as pools and woody debris.

Removing the culvert would lead to flushing of aggraded sediment and temporarily impact the downstream channel, which recently received fisheries habitat enhancement structures. To accelerate recovery and avoid downstream impacts, 1,100 ft (335 m) of upstream channel was regraded at the identified stable grade (1% slope) and 1,200 cy (920 m3) of sediment was removed.

The barrier was replaced with a 28 ft (8.5 m) wide pre-cast bottomless arch culvert placed on concrete strip footings. The top of the formed-in-place strip footings were constructed level with the channel design grade. The arch-culvert is wider than the active channel and of sufficient size to accommodate the passage of the 100-yr flow and associated substrate and debris. Two boulder weirs were constructed above the crossing to maintain channel grade, reduce additional sediment release, and improve fish habitat. Additionally, four boulder wing deflectors were installed to improve fish habitat. Upon completion, disturbed areas were revegetated with a native grass seed mixture, ferns, and over 250 native conifer and decidious trees to expand and diversify the riparian area.

An excellent public education opportunity presented itself with this fish passage project. Students from Margaret Keating Elementary, located next to Mynot Creek, participated in riparian planting efforts and made an educational display on salmon and stream restoration that was placed at the new crossing.

 

Post-Project Observations and Lessons Learned

Removing the aggraded sediment with heavy equipment appears to be an appropriate solution for this site for several reasons: (1) Mynot Creek was dry during construction, thereby avoiding the challenges and biological impacts associated with dewatering, (2) the channel completely lacked large wood and other elements that typically store and meter out sediment, and (3) the sediment was predominately fines and small gravel that would have temporarily impacted downstream habitat if released. These factors were considered when determining whether to remove the aggraded sediment, meter it out slowly using temporary grade control, or let it naturally regrade and transport the sediment downstream.

There continues to be post-project channel adjustment. After removing the sediment additional bedload mobilized during the first winter, resulting in aggradation within the culvert. Further post-project monitoring is needed to determine the sources of the mobilized sediment and if the channel has reached its new equilibrium. Currently there are plans to lower the two boulder grade control weirs to allow the channel bed to continue lowering.

Spawner surveys identified a coho salmon carcass upstream of the culvert the first winter after construction (2003). A spawning adult steelhead and a redd were observed just above the project area in 2004.