San Pedro Creek

Channel Restoration of Incised Channel to Eliminate Perched Bridge Apron

Case Study Contributors

  • Sydney Temple P.E.,
    Questa Engineering Corp.
  • Christine Chan, San Pedro Creek Watershed Coalition

Location
San Pedro Creek, City of Pacifica,
Northern California, USA. MAP

Project Type

  • Restoration of incised channel
  • Elimination of perched bridge apron

Pre-Project Conditions

  • Concrete box culvert, with failing Denil fish ladder retrofit
  • 12 foot drop at crossing
  • Incised and eroding channel

Pre-Project Barrier

  • Partial velocity and leap barrier for adult steelhead trout
  • Complete barrier for juvenile steelhead trout

Hydrologic Characteristics

  • Drainage Area: 8.2 mi2 (21.2 km2)
  • 100-year Flow: 3,000 cfs (85 cms)
  • 10-year Flow: 1,400 cfs (40 cms)
  • 2-year Flow: 350 cfs (9.9 cms)
  • Bankfull Width: 14-18 ft (4.3 – 5.5 m)
  • Pre-Project Channel Slope: 0.6-1%

Ecological Value

  • Provide upstream access to 2.2 miles (3.5 km) of high value spawning and rearing habitat for steelhead trout.
  • Improve fisheries habitat, reduce streambank erosion, and establish riparian vegetation in restored reach

Project Characteristics

  • Remove concrete Denil fish ladder and backfill bridge apron with substrate.
  • Restore 1,300 ft (396 m) of incised channel downstream of bridge apron to eliminate perched apron
  • Stabilize channel and promote pool-riffle formation with rock and log weirs
  • Raise and widen channel, reestablish floodplains, and stabilize banks

Challenges

  • Narrow easements and homes built to the top edge of stream bank limited the extent of floodplain creation.

Project Contributors

  • Questa Engineering Corp.
  • City of Pacifica
  • Water Resources Control Board
  • CA Department of Water Resources
  • American Rivers/NOAA

Project Funding

  • CA Coastal Conservancy
  • CA Dept. of Water Resources
  • CA Dept. of Fish and Game
  • CA Regional Water Quality Control Board
  • National Fish and Wildlife Foundation

Total Cost

Construction $ 1,593,691
Other $ 180,246

Total $ 1,773,937

Completion Date
November 2005


Project Description

The City of Pacifica restored approximately 1,300 linear feet (396 m) of San Pedro Creek downstream of the Capistrano Bridge, eliminating the perched bridge apron that was a steelhead migration barrier. The project reach was impaired due to severe down cutting of the channel, which resulted in perching the Capistrano Bridge apron 12 ft (3.7 m) above the downstream channel. The degraded riparian corridor downstream of the bridge was characterized by vertical, eroding banks and invasive plant species.

The Denil fish ladder was removed from under the bridge and the inlet apron was replaced with a series of temporary concrete weirs immediately upstream of the bridge. The weirs are to be removed during an upstream channel restoration project.

The streambed downstream of the crossing was raised and restored to provide access to the crossing, reduce bank erosion and restore riparian function. The channel dimensions were developed by the project geomorphologist to provide a stable, properly functioning channel. Width-depth ratios were reduced by increasing bankfull width and constructing small floodplains, which reduced scour forces on the channel bed.

To raise the channel bed, material was imported from a downstream regrading project and from laying back the banks in the project reach. The streambed was raised an average of 5 ft (1.5 m) through the project reach. A series of 26 rock and log weirs spaced 45 to 60 ft (14 to 18 m) apart were used to create a riffle/pool and step-pool channel with an average slope of 1.8%

Large wood-rock complexes were constructed to help direct flow and create meanders in the channel. The channel was seeded with large rock, allowing for natural accumulation of smaller materials. This caused the channel to rapidly develop a new profile, increasing the number and depth of pools after the first large flow.

Non-native landscape ornamentals along the channel banks were removed. Stream banks were regraded to stable slopes and then covered with erosion control materials and replanted with native riparian vegetation.

 

Post Project Observations and Lessons Learned

The log weirs placed on a rock foundation worked for this project but are likely near the maximum stream width for this technique.

Bed seeding (placement of only large material) allows fine material evacuation, scour and rapid pool development. However, it required an estimated 2 to 3 seasons to establish a gravel and sand substrate throughout the restored reach.

A large volume of rock was installed to depths up to ten feet to prevent the weirs from being undercut. However, at some locations flanking of the structures occurred and could have been avoided by keying additional rock further into the banks and directing the flow toward the center of the channel.

This project is an excellent example of how channel restoration can address multiple objectives of erosion control, habitat enhancement, and fish passage. Channel incision frequently creates barriers to fish passage at culverts and bridge aprons.  Removal of these barriers may allow downcutting to continue upstream, which can destabilize the upstream channel, degrade stream habitat, and threaten streamside structures. Using grade control immediately downstream of a crossing to eliminate the barrier only addresses fish passage and not the degraded downstream habitat.  In many instances it may be more appropriate to consider a larger scale project that includes restoring the downstream channel to its earlier grade. 


Published 09/25/07