Work Item Cost Factors
- FOREST SERVICE STANDARD FACTORS
- Design – 10%
- Contract Admin – 10%
- Overhead – 15%
- HERITAGE FACTOR
- REMOTENESS FACTOR (Only Factor Controlled by Field)
- Calculated From "Estimated Travel Time" Field
| Travel Time |
Cost Factor |
| 1 Hour (Default Setting) |
1 |
| 2 Hours |
1.5 |
| 4 Hours |
2 |
| 8 Hours |
3 |
| > 8 Hours |
4 |
|