Work Item Cost Factors

  • FOREST SERVICE STANDARD FACTORS
    • Design – 10%
    • Contract Admin – 10%
    • Overhead – 15%

  • HERITAGE FACTOR
    • Historic Buildings - 1.5

  • REMOTENESS FACTOR (Only Factor Controlled by Field)
    • Calculated From "Estimated Travel Time" Field
    Travel Time Cost Factor
    1 Hour (Default Setting) 1
    2 Hours 1.5
    4 Hours 2
    8 Hours 3
    > 8 Hours 4