Lake George Ranger Station Office Renovation Charrette

USDA Forest Service—Lake George Ranger Office Renovation Design Charrette

August 9-12, 2004

National Forests in Florida Ocala National Forest

Participants:

Randy Warbington,
Reg. Facility Engineer

Bill Speer,
Regional Architect

David Culp,
Regional Architect

Mason Miller,
LA/Rec Staff Officer

Jer Marr,
Lake George District Ranger

 

 

 

 

Kamal Otman,
NF in FL Engineer

Mark Warren,
NF in FL MERL Staff Officer

Tony Tooke,
NF in FL Deputy Forest Supervisor

Alison Thorn,
NF in FL Landscape Architect

Image of a design of a landscape with two buildings and a parking lot.

EXCERPT FROM BACKGROUND PAPER

and expand the Lake George Ranger Station Office. With the inclusion of cost pools, design, contract administration and interior furnishings the total projected cost is closer to $980,000. In July, the Forest Leadership Team will decide whether to provide Forest "small construction funds" in FY 2005 and 2006 to makeup the needed $350,000. Consideration was given to constructing a new office, but the price tag was prohibitive.

The project will involve renovating the existing office of 3,700 square feet and adding 2,050 square feet of new space. Through the use of Federal Highway funds and road construction funds the parking area and entrance/exit driveway would be relocated and a turn lane constructed off State Highway 40.

Due to the high visitation and visibility of the Lake George Ranger Station, the Regional Office would like to participate in an interdisciplinary design charrette using the Built Environment Image Guide. The team would consist of the Regional Office and Forest representatives. The process will take one week and involve the District Ranger at the opening to provide guidance and at the closeout.

The objective of the charrette is to agree on a concept for the office, parking and entrance driveway. This will occur in July or August of 2004. Following agreement on a concept the Forest will work with the Regional Office to complete a design and hopefully be prepared to advertise a construction contract in the spring of 2005 to correspond with the receipt of the $550,000 allocation in the FY 2005 Congressional budget.

DESIGN CHARRETTE SCHEDULE

Monday
6:30 -11:30

Travel to Site

Monday 12:30-2:30

Discuss objectives, orientation to BEIG and Sustainability; Line Officer Input.

Monday
3-5

Dedication, Alexander Springs, Visit other Local Projects.

Tuesday
8-10

Study global and regional influences—natural, cultural and regulatory—which are likely to affect the project.

Tuesday
10-12

Visit project site, interview Ranger’s Staff and affected personnel to collect applicable data, preconceptions, ideas, etc.

Tuesday
1-5

Discuss w/ team regional and local influences observed at or near the site, and how these might affect or translate into site and architectural character and/or project components. Consider regulatory issues and other project objectives as well. BEIG Video.

Wednesday
8-12

Explore conceptual site plan designs which incorporate the ideas discussed.

Wednesday
12-5

Explore building and system features and how these might integrate with the site. Discuss before drawing. Architect may provide conceptual sketches which illustrate ideas being considered. Actual preliminary floor plan and elevations to come later, but to be guided by the team’s decisions. Also possible materials and color scheme.

Thursday
7:30-9:30

Further refine presentation to Ranger and staff.

Thursday
9:30-11:30

Present the team’s concepts to the Ranger and staff for feedback.

ESTABLISHED DESIGN GUIDELINES

Site:

  • Preserve existing trees and vegetation
  • Develop a needed sign plan
  • Design lighting as required, but keep minimized
  • Design storm water system to comply with St. John’s Water management
  • Allow for adequate turning radius of large RVs (minimum 50’ inside radius)
  • Consider buffering
  • Landscaping plan needed; Consider xeriscaping and rainwater harvesting

B U I L D I N G :

  • Good indoor environmental quality
  • Low energy, low maintenance
  • Recycling and resource conservation
  • 7800 sf maximum; 1300 sf add alternate
  • Front entrance not to face Highway 40

E N T R A N C E / E X I T R O A D :

  • One central access point; Consider alternate fire exit
  • Entrance/Exit perpendicular to Highway 40
  • High visibility

P A R K I N G :

  • Existing = 34 FLEET / 60 EMPLOYEE / 6 PUBLIC
  • Proposed = 35 FLEET / 40 EMPLOYEE / 12 VISITOR (2 RV) / UNPAVED OVERLFOW

FINAL CONCEPTUAL DRAWINGS

Image of a conceptual drawing of an aerial view of a building site. Image of the Lake George design charrette.  Included are various images of houses, windows, colors, and structural designs.
Image of a design sketch of a building. Image of a design sketch of a building.
Image of a design sketch of a building and surrounding landscape.  