Common Recommendations
Specification Improvements
- Remove cut sheets from Div. 16 specs that aren't
used in project
- Delete requirements for "licensed Exterminator" in
Spec. 01310
- Delete "Energy Conservation Officer" and "Waste
Management Coordinator" I Spec 01310
- Clearly define and specify
parameters for sprinkler system design/build including supply connections,
controls to pump, blow-off, testing/monitoring,
etc…
Bidding Improvements
- Better bid period
- Allow generous time for completion of contract work
- Allow 6 weeks for
bid period
- Bid exhibits mfg. and exhibit installation separately (supply
contract vs. const—prevail. Wages—expertise)
- Ensure contractors
are aware of project (other than just fed biz ops)
- Acquisition Plan—Contact
CO
General
- Revise contract timing requirements—let Contractor have full
access to the site w/o FS interference (Robin felt they could operate
outside of exist. Bldg during Const.)
- Design Fire Sprinkler System prior to bidding project
again
- Use savings from water system (if any) for water/wastewater improvements
in LLVC
- Delete note J on sheet E2.2
- Coordinate with IT now!
- Develop Timeline w/ responsibilities