Catalyst Lot 475 Pipeline Special Use Proposal
Catalyst Energy Inc. has proposed the development of a new pipeline following along FR 169 within Pleasant Township, Warren County. The proposed Right of Way is approximately 2,000 feet in length by 15 feet wide, totaling about a 1 acre clearing.
Project Information
Expected Analysis Type
Decision Memo
Categorical Exclusion
Approval, modification, or continuation of special uses that require less than 20 acres of NFS lands.
Special Authority
Not applicable / Other
Lead Management Unit
Bradford Ranger District
Notice and Comment Regulation
215
Project Purpose
Special use management
Project Activity
Special use authorizations
Project Status
Current Status
Analysis Completed
Project Decision Information
Catalyst Energy, Inc. - Special Use Permit - Lot 475 Pipeline
Decision Signed Date
2012-06-12
Legal Notice Date
2012-06-15
Last Updated: 06/15/2012