Balcony Falls to Buena Vista Transmission Line Replacement
Dominion seeks to replace 115 kilovolt (kV) transmission lines that were constructed in the 1920s to maintain electric reliability. The lines run for approximately 20 miles from Dominion Skimmer substation to its Buena Vista substation.
Project Information
Expected Analysis Type
Environmental Assessment
Special Authority
Not applicable / Other
Lead Management Unit
George Washington and Jefferson National Forest All Units
Notice and Comment Regulation
218 (2013) Non-HFRA
Project Purpose
Special use management
Project Activity
Electric Transmission; Facility improvements/construction; Special use authorizations
Project Status
Current Status
Analysis Completed
Project Decision Information
Balcony Falls to Buena Vista Transmission Line Replacement
Decision Signed Date
2024-01-10