Mill Creek - Council Mountain [24]

RSS FeedSubscribe to this feed

The project area is approximately 50,000 acres. Vegetation treatments include mechanical, hand, and prescribed burning. Watershed improvements include existing road improvement and road decommissioning. Recreational improvements are also included.

Project Information

Expected Analysis Type
Environmental Impact Statement

Special Authority
Not applicable / Other

Lead Management Unit
Council Ranger District

Notice and Comment Regulation
215

Project Purpose
Fuels management; Forest products; Road management; Watershed management; Vegetation management (other than forest products)

Project Activity
Fuel treatments (non-activity fuels); Forest vegetation improvements; Species habitat improvements; Trail management; Noxious weed treatments; Travel management; Timber sales (green); Watershed improvements

Project Status

Current Status
Analysis Completed

Project Milestones
All planning milestones have been completed.

Project Decision Information

Mill Creek-Council Mountain Landscape Restoration Project ROD

Decision Signed Date
2012-04-06

Legal Notice Date
2012-04-06

Last Updated: 05/02/2018