South Fork Boise River Road Relocation

RSS FeedSubscribe to this feed

Relocate or rebuild Forest Road 227 at the large Bowns Washout in order to reconnect the road between Big Smoky and Featherville.

Project Information

Expected Analysis Type
Environmental Assessment

Special Authority
Not applicable / Other

Lead Management Unit
Fairfield Ranger District

Notice and Comment Regulation
Not Subject to Regulations

Project Purpose
Road management; Wildlife, Fish, Rare plants

Project Activity
Species habitat improvements; Road improvements/construction

Project Status

Current Status
Analysis Completed

Project Milestones
All planning milestones have been completed.

Project Decision Information

Forest Road 227 Realignment (Bowns Washout) Project

Decision Signed Date
2020-04-28

Last Updated: 04/29/2020