Indiana Creek Aquatic Organism Passage and Road Decommissioning

RSS FeedSubscribe to this feed

To create an Aquatic Organism Passage at the open water ford at the intersection of Indiana Creek and Pennsylvania Creek Rd. The 2nd objective is to decommission a 1.3 mi segment of a non-system FS road that is causing sediment and bank instability.

Project Information

Expected Analysis Type
Decision Memo

Categorical Exclusion
Restore, rehabilitate, or stabilize lands occupied by roads and trails(Road and trail rehablitation)

Special Authority
Not applicable / Other

Lead Management Unit
White River National Forest All Units

Notice and Comment Regulation
Not Subject to Regulations

Project Purpose
Watershed management; Wildlife, Fish, Rare plants; Road management

Project Activity
Road decommissioning; Species habitat improvements; Travel management; Watershed improvements

Project Status

Current Status
Analysis Completed

Project Milestones
All planning milestones have been completed.

Project Decision Information

Indiana Creek Aquatic Organism Passage Project

Decision Signed Date
2019-05-24