Sage Hen Integrated Restoration Project

The Forest Supervisor has published the Revised Environmental Assessment and Draft Decision Notice for the Sage Hen Project. This project is now in a 45-day administrative objection period.

Location Summary

Chief Eagle Eye Creek watershed north of High Valley and on the westside of the Emmett Ranger District. The eastside of the project area includes a portion of the Snowbank Roadless Area.

District: Emmett Ranger District

Project Milestones

MilestoneDate
Scoping Start04/15/2020
Comment Period01/19/2024
Objection Period Start03/20/2024
Decision06/01/2024 (Estimated)
Implementation07/01/2024 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public