Holy Cross Energy (HCE) Avon-to-Gilman Electric (115-kV) Transmission Line

RSS FeedSubscribe to this feed

Holy Cross Electric Association, Inc. proposes to construct 8.65 miles of new 115-kV transmission line between the Gilman and Avon substations along the Eagle River valley, crossing 3 miles of the White River National Forest and the Town of Minturn.

Project Information

Expected Analysis Type
Environmental Assessment

Special Authority
Not applicable / Other

Lead Management Unit
East Zone/Holy Cross Ranger District

Notice and Comment Regulation
218 (2013) Non-HFRA

Project Purpose
Special use management

Project Activity
Developed site management; Electric Transmission; Fuel treatments (non-activity fuels); Special use authorizations; Trail management; Noxious weed treatments; Road improvements/construction

Project Status

Current Status
Under Analysis

Project Milestones
Last Completed Milestone: Notice of Initiation (11/19/2019)
Next Milestone: Comment Period (est. 04/01/2021)

Last Updated: 03/19/2021