Clear Creek Forest Health Project
The Forest Supervisor of the Boise National Forest has signed the Decision Notice for the Clear Creek Forest Health Project. The signed Decision implements actions described in the project Environmental Assessment, Finding of No Significant Impact (EA-FONSI), and Draft Decision Notice (Draft DN). This project meets the requirements as part of the insect and disease treatment program in accordance with Title VI, Section 602, of the Healthy Forests Restoration Act (HFRA), as amended by the Agricultural Improvement Acts of 2014 and 2018 (2014 and 2018 Farm Bills). The signed Decision Notice and EA-FONSI-Draft DN can be found on the project homepage under the "Objection Period and Signed Decision" folder. 08/20/2022
Location Summary
The Clear Creek area is about 14 miles northeast of Boise, just west of Highway 21 via Clear Creek Road (NF-261).
District: Mountain Home Ranger District
Project Milestones
Milestone | Date |
---|---|
Scoping Start | 07/15/2021 |
Comment Period | 03/24/2022 |
Objection Period Start | 05/20/2022 |
Decision | 08/12/2022 |
Implementation | 08/01/2022 (Estimated) |
Project Documents
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public