Department of Energy-National Nuclear Security Administration(NNSA) Electrical Power Upgrade (EPCU)
NNSA proposes to construct and operate a 115 kV transmission line on the Santa Fe NF (SFNF) to meet anticipated power needs at the Los Alamos National Laboratory. This project includes amending the SFNF Land Management Plan under 36 CFR 219 Regs
Location Summary
Project activities proposed to occur on the Santa Fe National Forest located on the Caja del Rio, located to the west and northwest of Santa Fe, NM.
District: Santa Fe National Forest All Units
Project Milestones
Milestone | Date |
---|---|
Scoping Start | 01/15/2020 |
Comment Period | 01/22/2024 |
Objection Period Start | 09/11/2024 |
Decision | 01/01/2025 (Estimated) |
Implementation | 01/01/2025 (Estimated) |
Project Documents
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public