Flower Creek

This project includes fuel and vegetation management through commercial timber harvest, pre-commercial thinning and fuel grinding. Also includes 1.81 miles of road storage, 1 mile of temporary road construction, and 0.23 miles of trail construction.

Location Summary

Flower Creek watershed, 3 air miles south of Libby, Montana

District: Libby Ranger District

Project Milestones

MilestoneDate
NOI in Federal Register06/03/2009
DEIS NOA in Federal Register06/03/2009
FEIS NOA in Federal Register11/2015 (Estimated)
Objection Period Start10/2015 (Estimated)
Decision12/2015 (Estimated)
Implementation02/2016 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public

https://www.fs.usda.gov/project/kootenai/?project=29532