Seven Cabins Road Realignment

Aquisition of right of way road easement and construction of approx. 0.8-mile of new road to access Forest System Road 256 and ensure legal access to the north side of the Capitan Mountains.

Location Summary

North side of Capitan Mountains, FR 256

District: Smokey Bear Ranger District

Project Milestones

MilestoneDate
Scoping Start02/15/2012
Comment Period07/30/2014
Objection Period StartN/A
Decision09/15/2014
Implementation10/2014 (Estimated)

Project Documents

Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.

If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.

Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public