Omya Butterfield and Sentinel Quarries Expansion Project
Omya California is submitting to the Forest and County an amended Plan of Operations and Reclamation Plan for expansion of the Butterfield 3 and Sentinel Quarries.
Project Summary
Location Summary:
T.3 N., R.1 W., Sec.23
Project Milestones:
Milestone | Date |
---|---|
NOI in Federal Register | 02/28/2013 |
DEIS NOA in Federal Register | 07/13/2018 |
FEIS NOA in Federal Register | 12/27/2019 |
Objection Period Start | 12/27/2019 |
Decision | 06/2020 (Estimated) |
Implementation | 06/2020 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Not Applicable / Other
Lead Management Unit:
San Bernardino National Forest All Units
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Minerals And Geology
Project Activity:
Minerals Or Geology Plans Of Operations
Current Status:
Completed
Project Decision Information
Butterfield-Sentinel Quarry Expansion Project
Decision Signed Date: 06/09/2020
Forests:
San Bernardino National Forest
Districts:
Big Bear Ranger District
States:
California
Counties:
San Bernardino
Legal Land Description:
Omya Butterfield 3 unpatented mining claims
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Scott Eliason
602 S. Tippecanoe Ave
San Bernardino, CA 92408
909-382-2830
seliason@fs.fed.us
Last Updated: 6/9/2020