FS-29 Road Restoration Complete

Olympic National Forest

April 16, 2026

Updated October 15, 2026 - The $3.5 million ERFO‑funded FS‑29 road rehabilitation project is now complete. Crews repaired nine major washout sites caused by past atmospheric river events and upsized multiple culverts to improve resilience during future storms. While not confirmed, engineers believe this may be the largest construction project ever completed on the Olympic National Forest.

Please note: The road remains closed at milepost 23.9 due to a separate road failure that was not part of the ERFO project. Additional efforts are underway to address this site and restore full access. 

Image

Map of sites along FS-29 that were impacted by 2021 atmospheric rivers. 

(USFS)

In November 2021, a category 5 atmospheric river dropped more than 10 inches of rain over 24 hours across the Olympic National Forest. The Forks area, already saturated from persistent fall storms, was heavily impacted. The extreme runoff triggered multiple debris flows and washouts along Forest Service Road 29 (FS‑29).

Since then, the Olympic National Forest has worked closely with local, county, and federal partners, including the Federal Highway Administration, to restore access along FS‑29. This effort has included reinforcing road segments and upgrading culverts to improve drainage capacity, increase resilience, and reduce the risk of damage during future flood events.

The final phase of this project is now underway, with large‑scale construction scheduled to begin on the remaining nine sites this spring. Contractors are currently conducting preliminary survey work in preparation for road construction. 

Between the end of April and October, multiple closures will be required along FS‑29, to ensure safety which will limit access to forest lands and waterways. The following construction schedule is tentative and may change based on weather conditions, site conditions, or other dynamic factors.

 

Site 

Estimated Start Date

Estimated End Date

Estimated Time

Closure Order

Road 

Mile Post 

2922 

3.1 

5/04/2026

5/15/2026 

10 days 

Work complete

2922 

5.1 

5/20/2026 

6/4/2026 

12 days 

Work complete

2900 

33.9 

5/27/2026 

7/2/2026 

27 days

Work complete

2900

30.3

7/6/2026

7/20/2026

11 days

Work complete

2900 

11.1 

7/20/2026 

7/31/2026 

11 days 

Work complete

2900 

2.8 

8/10/2026

8/26/2026

16 days 

Work complete

2900 

3.1 

8/10/2026

8/26/2026

8 days 

Work complete

2900 

7.5 

8/29/2026 

9/9/2026 

8 days 

Work complete

2900 

7.55 

9/9/2026 

9/30/2026 

20 days 

Work complete

2900

all

10/7/2026

10/12/2026

5 days

Work complete

Paving and hydroseeding of the road is occurring the week of October 5th with the final inspection and opening of the road the following week. 

Related: Press Release, April 16, 2026

Last updated October 15, 2026