Report Contents (click to jump to a section) : - Projects Occurring Nationwide - R8 - Southern Region, Cherokee National Forest, Forestwide (excluding Projects occurring in more than one Forest) - R8 - Southern Region, Cherokee National Forest, Occurring in more than one District (excluding Forestwide) - R8 - Southern Region, Cherokee National Forest, Ocoee - Hiwassee Ranger District (excluding Projects occurring in more than one District) - R8 - Southern Region, Cherokee National Forest, Tellico Ranger District (excluding Projects occurring in more than one District) - R8 - Southern Region, Cherokee National Forest, Unaka Ranger District (excluding Projects occurring in more than one District) - R8 - Southern Region, Cherokee National Forest, Watauga Ranger District (excluding Projects occurring in more than one District) | |||||
Projects Occurring Nationwide |
|||||
Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
---|---|---|---|---|---|
Land Management Plan Direction for Old-Growth Forest Conditions Across the National Forest System EIS *UPDATED* |
- Land management planning |
In Progress: DEIS NOA in Federal Register 06/21/2024 Est. FEIS NOA in Federal Register 12/2024 |
Expected:01/2025 |
01/2025 |
Jennifer McRae 202-791-8488 SM.FS.NFSWONGA@usda.gov |
Description: Amend all land management plans for units of the National Forest System to include consistent direction to conserve and steward existing and recruit future old-growth forest conditions and to monitor their condition across planning areas of NFS.
Web Link: http://www.fs.usda.gov/project/?project=65356 |
|||||
Location: UNIT - All Districts-level Units. STATE - All States. COUNTY - All Counties. LEGAL - Not Applicable. National Forests and Grasslands (128 units). | |||||
Locatable Mining Rule - 36 CFR 228, subpart A. EIS |
- Regulations, Directives, Orders | On Hold | N/A | N/A |
Sarah Shoemaker 907-586-7886 sarahshoemaker@fs.fed.us |
Description: The U.S. Department of Agriculture proposes revisions to its regulations at 36 CFR 228, Subpart A governing locatable minerals operations on National Forest System lands.A draft EIS & proposed rule should be available for review/comment in late 2020
Web Link: http://www.fs.usda.gov/project/?project=57214 |
|||||
Location: UNIT - All Districts-level Units. STATE - All States. COUNTY - All Counties. LEGAL - Not Applicable. These regulations apply to all NFS lands open to mineral entry under the US mining laws. More Information is available at: https://www.fs.usda.gov/science-technology/geology/minerals/locatable-minerals/current-revisions. | |||||
Back To Top | |||||
Cherokee National Forest, Forestwide (excluding Projects occurring in more than one Forest) |
R8 - Southern Region | ||||
Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
Southern Appalachian Watershed Resiliency Project EA *NEW LISTING* |
- Wildlife, Fish, Rare plants - Vegetation management (other than forest products) - Watershed management - Road management - Projects that may affect Wilderness (for mailing list contacts) |
Developing Proposal Est. Scoping Start 07/2024 |
Expected:05/2025 | 06/2025 |
Jessie Howard 540-492-1728 jessie.howard@usda.gov |
Description: The Southern Appalachian Forests(Cherokee National Forest, George Washington and Jefferson National Forests, National Forests in North Carolina and Chattahoochee - Oconee National Forest seek to implement large landscape watershed resiliency efforts.
Web Link: http://www.fs.usda.gov/project/?project=66473 |
|||||
Location: UNIT - Cherokee National Forest All Units. STATE - Tennessee. COUNTY - Carter, Cocke, Greene, Johnson, McMinn, Monroe, Polk, Sullivan, Unicoi, Washington. LEGAL - Not Applicable. The entirety of the Cherokee National Forest. | |||||
Back To Top | |||||
Cherokee National Forest, Occurring in more than one District (excluding Forestwide) |
R8 - Southern Region | ||||
Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
Fiscal Year 2024 Prescribed Fire Project CE |
- Vegetation management (other than forest products) - Fuels management |
In Progress: Scoping Start 07/11/2023 |
Expected:09/2023 |
10/2023 |
Justin Feeman 423-397-8405 justin.feeman@usda.gov |
Description: The Fiscal Year 2024 Prescribed Fire Project would conduct prescribed fire on 41,919 acres on 28 burn units: 15 burn units on the Ocoee/Hiwassee Ranger District and 13 burn units on the Tellico Ranger District.
Web Link: http://www.fs.usda.gov/project/?project=64609 |
|||||
Location: UNIT - Ocoee - Hiwassee Ranger District, Tellico Ranger District. STATE - Tennessee. COUNTY - Monroe, Polk. LEGAL - Not Applicable. The project is located in multiple locations in Polk and Monroe Counties in Tennessee. | |||||
Back To Top | |||||
Cherokee National Forest, Ocoee - Hiwassee Ranger District (excluding Projects occurring in more than one District) |
R8 - Southern Region | ||||
Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
Bullet Creek Botanical Area Habitat Enhancement Project CE *NEW LISTING* |
- Wildlife, Fish, Rare plants | Completed | Actual: 05/16/2024 | 10/2024 |
Justin Feeman 423-397-8405 Justin.Feeman@usda.gov |
Description: The project would repair and reconstruct a woven wire fence within the Bullet Creek Rare Community to prevent feral swine / wild boar from entering and damaging this unique and rare ecosystem. The existing fence would be removed from the site.
Web Link: http://www.fs.usda.gov/project/?project=65840 |
|||||
Location: UNIT - Ocoee - Hiwassee Ranger District. STATE - Tennessee. COUNTY - McMinn. LEGAL - Not Applicable. Project is located east of Etowah, TN. | |||||
June 2024 RallyUSA Rally Car Race Project CE *UPDATED* |
- Special use management | Completed | Actual: 05/14/2024 | 06/2026 |
Philip Earhart 423-253-8416 philip.earhart@usda.gov |
Description: Special Use Permit to host rally car race on the Ocoee Ranger District for June 12-17.The race would utilize National Forest System Roads (NFSR) 23, 44, 55, 67, 99, 103, 220, 221, 302, and 1333. Four areas are identified for spectators.
Web Link: http://www.fs.usda.gov/project/?project=65892 |
|||||
Location: UNIT - Ocoee - Hiwassee Ranger District. STATE - Tennessee. COUNTY - McMinn, Monroe, Polk. LEGAL - Not Applicable. The project is located primarily in Polk County. Small portions are located in McMinn and Monroe Counties. | |||||
Ocoee Hiwassee Admin Site Area Release CE |
- Vegetation management (other than forest products) - Fuels management |
In Progress: Scoping Start 09/05/2019 |
Expected:11/2019 |
01/2020 |
Stephanie Medlin 423-476-9740 sm.fs.r8chertelcom@usda.gov |
Description: Treatments would include the severing of selected stems (chainsaw/manual), application of herbicide, and the use of prescribed fire within the designated unit (212 acres.
Web Link: http://www.fs.usda.gov/project/?project=56628 |
|||||
Location: UNIT - Ocoee - Hiwassee Ranger District. STATE - Tennessee. COUNTY - Polk. LEGAL - Not Applicable. Around the Ocoee/Hiwassee District Office. | |||||
Restoration of Dry Forest Communities Kirkland Gap Project EA *UPDATED* |
- Forest products - Vegetation management (other than forest products) - Fuels management |
In Progress: Objection Period Legal Notice 05/23/2024 |
Expected:07/2024 |
09/2024 |
Justin Feeman 423-397-8405 justin.feeman@usda.gov |
Description: The project would conduct forest restoration and improvement actions under the programmatic environmental assessment, Restoration of Dry Forest Communities. Additional actions in the project area would include road improvements and prescribed fire.
Web Link: http://www.fs.usda.gov/project/?project=64455 |
|||||
Location: UNIT - Ocoee - Hiwassee Ranger District. STATE - Tennessee. COUNTY - Polk. LEGAL - Not Applicable. The project is located in Polk County Tennessee approximately 2 miles north west of Turtletown, TN. | |||||
South Zone Trail Maintenance Project CE |
- Recreation management |
In Progress: Scoping Start 02/02/2022 |
Expected:03/2022 |
04/2022 |
Justin Feeman 423-397-8405 SM.FS.r8chertelcom@usda.gov |
Description: This project would allow routine maintenance on existing trails on the south zone of the Cherokee National Forest and minor reroutes where ground disturbance from natural events, such as tree windfall or landslide, are causing resource damage.
Web Link: http://www.fs.usda.gov/project/?project=61551 |
|||||
Location: UNIT - Ocoee - Hiwassee Ranger District. STATE - Tennessee. COUNTY - McMinn, Monroe, Polk. LEGAL - Not Applicable. Project includes all existing trails on the south zone of the Cherokee National Forest. | |||||
Starr Mountain Land Purchase CE |
- Land acquisition |
In Progress: Scoping Start 02/24/2022 |
Expected:03/2022 |
06/2022 |
Justin Feeman (423) 338-3300 SM.FS.r8cherococom@usda.gov |
Description: The project would acquire approximately 153 acres on Starr Mountain in McMinn County, TN. The parcel is adjacent to Gee Creek Wilderness and would be managed under the 7.B Scenic Corridor/Sensitive Viewsheds prescription.
Web Link: http://www.fs.usda.gov/project/?project=61680 |
|||||
Location: UNIT - Ocoee - Hiwassee Ranger District. STATE - Tennessee. COUNTY - McMinn. LEGAL - Not Applicable. The project is located approximately 4 miles south of Etowah, TN. | |||||
Stephens Access Road CE |
- Special use management | On Hold | N/A | N/A |
Terinda Whisenant 423-338-3300 fs-comments-southern-cherokee-ocoee-hiwassee@fs.fed.us |
Description: Applicant has requested access across NFS lands to an inholding that is completely surrounded. An existing route at the end of NFSR 366C is in place but has grown up and is not drivable. Heavy equipment would be used to clear this 150 ft. | |||||
Location: UNIT - Ocoee - Hiwassee Ranger District. STATE - Tennessee. COUNTY - Polk. LEGAL - Not Applicable. East of Hwy 30 and North of Hwy 64 in the Vicinity of the 4-H camp. | |||||
Back To Top | |||||
Cherokee National Forest, Tellico Ranger District (excluding Projects occurring in more than one District) |
R8 - Southern Region | ||||
Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
Lower Citico Dam Removal Project CE *NEW LISTING* |
- Watershed management |
In Progress: Scoping Start 04/18/2024 |
Expected:07/2024 |
09/2024 |
Nancy Gibson 530-543-2600 nancy.gibson@usda.gov |
Description: The project would remove an instream concrete dam at river mile 8.3 near Young Branch in Citico Creek. The dam would be removed with heavy machinery in a live or wet stream. All dam materials would be removed from the site.
Web Link: http://www.fs.usda.gov/project/?project=66092 |
|||||
Location: UNIT - Tellico Ranger District. STATE - Tennessee. COUNTY - Monroe. LEGAL - Not Applicable. Project is located approximately 13 miles Northeast of Tellico Plains, TN, at river mile 8.3 on Citico Creek, near Young Branch Campground. | |||||
Back To Top | |||||
Cherokee National Forest, Unaka Ranger District (excluding Projects occurring in more than one District) |
R8 - Southern Region | ||||
Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
Margarette Falls Trail #189 - Relocation Project CE |
- Recreation management |
In Progress: Scoping Start 03/17/2023 |
Expected:04/2023 |
05/2023 |
Seong Hopkins 423-782-2400 seong.hopkins@usda.gov |
Description: This project is proposing to relocate approximately a 50 ft long section of trail #189. Waterbars would also be installed to limit stormwater runoff and continued damage to the trail.
Web Link: http://www.fs.usda.gov/project/?project=63721 |
|||||
Location: UNIT - Unaka Ranger District. STATE - Tennessee. COUNTY - Greene, Unicoi. LEGAL - Not Applicable. Margarette Falls Trail #189. | |||||
North Zone Large Tracts Amendment CE |
- Land management planning | On Hold | N/A | N/A |
Jonathan Lampley 423-783-2416 jonathan.lampley@usda.gov |
Description: The proposed forest plan amendment would address the need to assign management prescriptions to four tracts of land that were previously acquired.
Web Link: http://www.fs.usda.gov/project/?project=62033 |
|||||
Location: UNIT - Unaka Ranger District. STATE - Tennessee. COUNTY - Carter, Johnson, Unicoi, Washington. LEGAL - Not Applicable. North Zone Cherokee National Forest. | |||||
Back To Top | |||||
Cherokee National Forest, Watauga Ranger District (excluding Projects occurring in more than one District) |
R8 - Southern Region | ||||
Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
Dry Creek Tract U-1637 Land Acquisition Project CE |
- Land acquisition |
Developing Proposal Est. Scoping Start 03/2024 |
Expected:04/2024 | 05/2024 |
Jay Chapman 423-476-9782 jay.chapman@usda.gov |
Description: The Forest Service is proposing to acquire 1 parcel in Unicoi County, TN (U-1637), approximately 67 acres.
Web Link: http://www.fs.usda.gov/project/?project=65825 |
|||||
Location: UNIT - Watauga Ranger District. STATE - Tennessee. COUNTY - Unicoi. LEGAL - Not Applicable. USA Tract U-1637 on the waters of Dry Creek in Unicoi County, TN. | |||||
Johnson County Communication Tower Project CE |
- Special use management |
Developing Proposal Est. Scoping Start 02/2024 |
Expected:03/2024 | 04/2024 |
Matthew Gilbert 423-743-5925 matthew.gilbert2@usda.gov |
Description: Johnson County is proposing to erect a 120-foot free-standing metal power pole and a 10x12 concrete building to house radio components and a generator. The pole and building would be constructed on a gravel pad and surrounded by a chain-link fence.
Web Link: http://www.fs.usda.gov/project/?project=65670 |
|||||
Location: UNIT - Watauga Ranger District. STATE - Tennessee. COUNTY - Johnson. LEGAL - Not Applicable. Iron Mountain in Johnson County, TN. | |||||
Pond Mountain Project EA |
- Wildlife, Fish, Rare plants - Forest products - Vegetation management (other than forest products) - Fuels management - Road management |
In Progress: Scoping Start 01/18/2023 Est. Comment Period Public Notice 05/2023 |
Expected:09/2023 |
01/2024 |
Jonathan Lampley 404-347-5264 jlampley@fs.fed.us |
Description: The project would provide early successional forest for wildlife, restore forest and wetland comm., release mast-producing trees, improve forest health, provide wildlife habitat components, and manage NFS system and non-system roads
Web Link: http://www.fs.usda.gov/project/?project=63431 |
|||||
Location: UNIT - Watauga Ranger District. STATE - Tennessee. COUNTY - Sullivan. LEGAL - Not Applicable. The project is located in Carter County, TN. The area is bounded by the Walnut Mountain Road on the eastern side, Laurel Fork Road on the Northern edge and the Appalachian Trail on the west and south. | |||||
SkyBest Communications Improvement Project CE |
- Special use management |
Developing Proposal Est. Scoping Start 02/2024 |
Expected:04/2024 | 04/2024 |
Matthew Gilbert 423-743-5925 matthew.gilbert2@usda.gov |
Description: SkyBest is proposing to bury fiber optic cable along U.S. Route 321 to increase grid reliability in new service areas in Carter County, TN.
Web Link: http://www.fs.usda.gov/project/?project=65698 |
|||||
Location: UNIT - Watauga Ranger District. STATE - Tennessee. COUNTY - Carter. LEGAL - Not Applicable. Near Watauga Point along U.S. Route 321 in Carter County, TN. | |||||
In accordance with Federal civil rights law and U.S. Department of Agriculture (USDA) civil rights regulations and policies, the USDA, its Agencies, offices, and employees, and institutions participating in or administering USDA programs are prohibited from discriminating based on race, color, national origin, religion, sex, gender identity (including gender expression), sexual orientation, disability, age, marital status, family/parental status, income derived from a public assistance program, political beliefs, or reprisal or retaliation for prior civil rights activity, in any program or activity conducted or funded by USDA (not all bases apply to all programs). Remedies and complaint filing deadlines vary by program or incident.
Persons with disabilities who require alternative means of communication for program information (e.g., Braille, large print, audiotape, American Sign Language, etc.) should contact the responsible Agency or USDA’s TARGET Center at (202) 720-2600 (voice and TTY) or contact USDA through the Federal Relay Service at (800) 877-8339. Additionally, program information may be made available in languages other than English. To file a program discrimination complaint, complete the USDA Program Discrimination Complaint Form, AD-3027, found online at http://www.ascr.usda.gov/complaint_filing_cust.html and at any USDA office or write a letter addressed to USDA and provide in the letter all of the information requested in the form. To request a copy of the complaint form, call (866) 632-9992. Submit your completed form or letter to USDA by: (1) mail: U.S. Department of Agriculture Office of the Assistant Secretary for Civil Rights 1400 Independence Avenue, SW Washington, D.C. 20250-9410; (2) fax: (202) 690-7442; or (3) email: program.intake@usda.gov. USDA is an equal opportunity provider, employer, and lender. |