Elk Smith Project
The purpose of the Elk Smith Project is to address fuel accumulation and continuity in the project area.
Project Summary
Location Summary:
Located in the Elk and Smith Creek drainages on the southern end of the Rocky Mountain Ranger District.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 08/14/2013 |
Comment Period | 04/12/2019 |
Objection Period Start | 04/12/2019 |
Decision | 11/2019 (Estimated) |
Implementation | 12/2019 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Rocky Mountain Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Vegetation Management (Other Than Forest Products); Fuels Management
Project Activity:
Fuel Treatments (Non-Activity Fuels)
Current Status:
Completed
Project Decision Information
Elk Smith Project
Decision Signed Date: 11/01/2019
(Constrained Due to Litigation)
Forests:
Lewis And Clark National Forest
Districts:
Rocky Mountain Ranger District
States:
Montana
Counties:
Lewis and Clark
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Corey Buhl
2880 Skyway Drive
Helena, MT 59601
406-683-3870
cbuhl@fs.fed.us
Last Updated: 11/3/2019