Major Fenn Side Channel Reconnection
Remove a section of raised gabion basket trail and create a 'persuasion' channel to allow river flow to enter a side channel of the Lochsa River. The project will restore approx. 0.3 mi of potentially valuable rearing habitat for juvenile salmonids
Project Summary
Location Summary:
Township 33 North, Range 8 East, Section 5; Idaho County, Idaho
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 01/31/2018 |
Decision | 02/2018 (Estimated) |
Implementation | 07/2018 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (18), 36 Cfr 220.6(E)(18)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Lochsa/Powell Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Wildlife, Fish, Rare Plants; Watershed Management
Project Activity:
Species Habitat Improvements; Species Population Enhancements; Watershed Improvements
Current Status:
Completed
Project Decision Information
Major Fenn Side Channel Reconnection
Decision Signed Date: 02/20/2018
Forests:
Nez Perce-Clearwater National Forest
Districts:
Lochsa/Powell Ranger District
States:
Idaho
Counties:
Idaho
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Rebecca Lloyd
502 Lowry
Kooskia, ID 83539
(208)926-8939 at Fenn/(208)942-0350 Powell
rebeccalloyd@fs.fed.us
Last Updated: 2/21/2018