Ross Waterline Replacement
This project would involve installing 4,500 feet of high density polyethylene (HDPE) line in the Red Canyon recreation corridor. This includes the installation of components such as drains, valve boxes, air vents, and other water control devices.
Project Summary
Location Summary:
West Greens Lake to Red Canyon Visitor Center in the Red Canyon recreation corridor
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/28/2025 |
Decision | 04/2025 (Estimated) |
Implementation | 06/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (22), 36 Cfr 220.6(E)(22)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Flaming Gorge Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Recreation Management; Facility Management
Project Activity:
Facility Maintenance
Current Status:
Completed
Project Decision Information
Ross Waterline Replacement
Decision Signed Date: 04/17/2025
Forests:
Ashley National Forest
Districts:
Flaming Gorge Ranger District
States:
Utah
Counties:
Daggett
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Mairin Glenney
25 West Highway 43
Manila, UT 84046
540 525-9587
Mairin.Glenney@usda.gov
Last Updated: 4/18/2025