Forest Road 52 Realignment
The project would realign Forest Road (FR) 52 so that it branches off of FR 50, directly south of the Barker Spring Loop cattleguard. We would also replace the associated Little Brush Creek gate with fencing.
Project Summary
Location Summary:
Forest Service Road 52 runs along the south ridge of Dutch Charles Draw.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 02/28/2025 |
Decision | 04/2025 (Estimated) |
Implementation | 06/2025 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (24), 36 Cfr 220.6(E)(24)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Vernal Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Grazing Management; Road Management
Project Activity:
Road Improvements/Construction; Grazing Structural Improvements
Current Status:
Completed
Project Decision Information
Forest Road 52 Realignment
Decision Signed Date: 04/15/2025
Forests:
Ashley National Forest
Districts:
Vernal Ranger District
States:
Utah
Counties:
Uintah
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Todd Irish
355 North Vernal Ave
Vernal, UT 84078
435-781-5205
todd.irish@usda.gov