Idaho Power Bogus Basin Underground Line Placement Project
Idaho Power proposes to install new underground power cables to the top of Shafer Butte and Deer Point at Bogus Basin. The existing cables that provide power to these two areas of critical facilities are deteriorating.
Project Summary
Location Summary:
Bogus Basin Recreation Area, 16 miles north of Boise via Bogus Basin Road.
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 04/19/2021 |
Decision | 12/2021 (Estimated) |
Implementation | 05/2022 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Mountain Home Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Developed Site Management; Special Use Authorizations
Current Status:
Completed
Project Decision Information
Idaho Power Bogus Basin Underground Line Placement Special Use Permit
Decision Signed Date: 12/13/2021
Forests:
Boise National Forest
Districts:
Mountain Home Ranger District
States:
Idaho
Counties:
Boise
Legal Land Description:
Not Applicable
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Brian Lawatch
3080 Industrial Way
Mountain Home, ID 83647
208-590-3345
brian.lawatch@usda.gov