Wapiti Creek Trailhead Relocation (Forest Trail 160)
Relocate the trailhead to better allow for multiple uses and provide safer parking and vehicle maneuverability.
Project Summary
Location Summary:
NFSR 525A and Trail 160
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 10/05/2022 |
Comment Period | 10/05/2022 |
Objection Period Start | 03/08/2023 |
Decision | 05/2023 (Estimated) |
Implementation | 06/2023 (Estimated) |
Expected Analysis Type:
Environmental Assessment
Special Authority:
Not Applicable / Other
Lead Management Unit:
Lowman Ranger District
Notice and Comment Regulation:
218 (2013) Non-HFRA
Project Purpose:
Road Management; Recreation Management
Project Activity:
Trail Management; Travel Management
Current Status:
Completed
Project Decision Information
Wapiti Creek Trailhead Relocation (Forest Trail 160)
Decision Signed Date: 05/03/2023
Forests:
Boise National Forest
Districts:
Lowman Ranger District
States:
Idaho
Counties:
Boise
Legal Land Description:
Section 32 of T10N,R11E
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Catharine Beverly-Bishop
Highway 21
Lowman, ID 83637
208-365-7001
Catharine.Beverly-Bishop@usda.gov
Last Updated: 5/8/2023