Sigurd to Red Butte 345 kV Transmission Line
Construct a new 345 kV transmission line connecting the Sigurd substation located near Richfield, UT to the Red Butte substation located near Central, UT.
Project Summary
Location Summary:
Linear alignment from approximately 6 miles northeast of Richfield, UT to just southwest of the town of Central, UT
Project Milestones:
Milestone | Date |
---|---|
NOI in Federal Register | 01/05/2010 |
DEIS NOA in Federal Register | 06/03/2011 |
FEIS NOA in Federal Register | 10/05/2012 |
Decision | 12/2012 (Estimated) |
Implementation | 04/2013 (Estimated) |
Expected Analysis Type:
Environmental Impact Statement
Special Authority:
Not Applicable / Other
Lead Management Unit:
Pine Valley Ranger District
Notice and Comment Regulation:
215
Project Purpose:
Special Use Management
Project Activity:
Special Use Authorizations
Current Status:
Completed
Project Decision Information
Sigurd to Red Butte No. 2 - 345kV Transmission Project Record of Decision
Decision Signed Date: 12/07/2012
Legal Notice Date: 12/12/2012
Forests:
Dixie National Forest; Fishlake National Forest
Districts:
Pine Valley Ranger District; Fillmore Ranger District; Beaver Ranger District
States:
Utah
Counties:
Beaver; Iron; Millard; Sevier; Washington
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Charles Call
196 E. Tabernacle, Suite 40
St. George, UT 84770
435-865-3730
ckcall@fs.fed.us
Last Updated: 12/21/2012