Verizon Solar Panel at Aldrich Communication Site
Verizon Wireless to add 65' X 9' of new solar panels (15 panel sections) to the existing communication sites solar power system.
Project Summary
Location Summary:
Aldrich Mountain communication site
Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/29/2020 |
Decision | 04/2021 (Estimated) |
Implementation | 06/2021 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (3), 36 Cfr 220.6(E)(3)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Malheur National Forest All Units
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Special Use Management
Project Activity:
Facility Improvements/Construction
Current Status:
Completed
Project Decision Information
Verizon Solar Panel at Aldrich Communication Site
Decision Signed Date: 04/22/2021
Forests:
Malheur National Forest
Districts:
Blue Mountain Ranger District
States:
Oregon
Counties:
Grant
Legal Land Description:
Section 11, T. 14 S., R. 27 E., Willamette Meridian
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Stacia Kimbell
431 Patterson Bridge Road
John Day, OR 97845
541-575-3349
skimbell@fs.fed.us
Last Updated: 5/11/2021