Project Milestones:
Milestone | Date |
---|---|
Scoping Start | 06/16/2012 |
Decision | 07/2013 (Estimated) |
Implementation | 07/2013 (Estimated) |
Expected Analysis Type:
Decision Memo
Categorical Exclusion:
32.2 (13), 36 Cfr 220.6(E)(13)
Special Authority:
Not Applicable / Other
Lead Management Unit:
Cle Elum Ranger District
Notice and Comment Regulation:
Not Subject to Regulations
Project Purpose:
Fuels Management
Project Activity:
Fuel Treatments (Non-Activity Fuels)
Current Status:
Cancelled
Forests:
Okanogan-Wenatchee National Forest
Districts:
Cle Elum Ranger District
States:
Washington
Counties:
Kittitas
Legal Land Description:
Sec. 26, T. 21 N., R. 12 E.
Use the widget below to browse documents associated with this project. Cookies must be enabled to use this tool.
If you are using a mobile device, the setting for "Allow cross-website tracking" must also be enabled to view the documents. You do not need to sign up or login to Box to view documents, but if you have difficulty accessing the documents on a mobile device, you may choose to sign up for a free account, download the app to your device and log in to ensure that you can open the documents.
Alternatively, these documents can be accessed on the Pinyon Public website: View Documents on Pinyon Public
Shan Madden
803 W. 2nd Street
Cle Elum, WA 98922
509-852-1031
smadden@fs.fed.us
Last Updated: 3/26/2013