New Buildings Work Item Screen Features
- Burden of cost estimating removed from the condition survey process
- Costs automatically updated annually via RS Means
- Consistent, Repeatable, Defendable process as required by OIG
- Tabs: Basic, Complex, RS Assem, RS Unit dollars
- Custom Work Items—Coming Soon, Recommended to be used only
when Basic, Complex, RS Assem, RS Unit dollars tabs do not contain
needed item
- Basic Buildings—All buildings with no mechanical, electrical,
plumbing systems, approximately 30,000 FS facilities
- Basic and Complex forms appear by default to Category and Subcategory,
but can be changed by selecting the alternate form when appropriate
- Work items needed prior to next survey can be entered by populating
the "Planned Start Date" and selecting "Annual
Maintenance" task type
- If "Planned Start Date" of a task passes before task
is checked "Complete", the task type will automatically
change to "Deferred Maintenance"
|