|
Reference
Documents
| Because of
the size of this document, it has been broken down
into five sections. For hard copies of the
Environmental Assessment please call Mary O'Brien at
202-205-1318. |
<<
Previous Section 1 - 2
- 3 - 4
- 5 Next
Section >>
Alternatives Eliminated
The following alternatives or components of alternatives
were developed but eliminated from detailed consideration.
Suspend all projects in unroaded areas. This
option would suspend all projects in addition to permanent
and temporary road construction and reconstruction in
unroaded areas of NFS lands, which would extend the scope of
the analysis to include all activities and would include
timber harvesting, off-road vehicle use, grazing, and
mining. The purpose of the proposed temporary suspension is
to preserve the resource options of unroaded areas of NFS
lands from potentially adverse effects associated with
permanent and temporary road construction and reconstruction
while adopting a revised road management policy. Suspension
of all projects is beyond the purpose of and need for this
action.
Apply suspensions to any unroaded area of 1,000 acres or
more. This option would apply the proposed temporary
suspension to any unroaded area 1,000 acres or more
regardless of its proximity to inventoried roadless areas.
Current inventories are used as the basis for identifying
areas subject to suspension because these roadless areas
have been validated through the forest planning process as
providing important ecological values. While 1,000 acre
blocks, regardless of their proximity to inventoried
roadless areas may in fact be unroaded, such areas have not
been inventoried nor validated as part of forest planning.
Adding these areas would extend the geographic scope of the
proposed temporary suspension beyond the identified purpose
and need. During the RARE II and land management planning
process, inventories of unroaded areas of various sizes have
already been considered. The suspension is not intended to
re-create another inventory of unroaded areas or adjust land
management plans. Regional Foresters have the authority to
approve, reject, or suspend individual road construction
projects on their units. No new authorities or limitations
are needed because Regional Foresters may suspend road
construction projects outside RARE II areas during the
proposed temporary suspension.
Table 3. Estimated and suspended permanent and temporary
road construction and reconstruction miles on National
Forest System lands, by alternative, during the proposed
temporary suspension.1

1
Numbers may not total due to rounding. Where
conflicts occur due to rounding, original data was used.
2 All miles on roaded and unroaded areas
of National Forest System lands.
3 All miles in unroaded areas of National
Forest System lands.
Apply suspensions to
municipal watersheds.
This action would apply the proposed temporary suspension of
permanent and temporary road construction and reconstruction
to municipal watersheds. For public supply watersheds, the
Safe Drinking Water Amendments of 1996 require States and
tribes to assess their vulnerability to pollution from
existing and known future sources and to submit protection
programs within 2 years for Environmental Protection Agency
(EPA) approval. The Forest Service is working with States,
tribes, and the EPA to help delineate, assess, and protect
public watershed supplies. There will be local,
collaborative efforts to determine the boundaries of these
watersheds and how best to protect the water supplies. The
Forest Service recognizes a special need to carefully manage
lands that fall within the 900 municipal watersheds it
administers. In addition to regulations, Forest Service
Manual 2543 provides specific guidance on protection of
municipal watersheds including how to identify and designate
municipal watersheds, address them in forest plans, restrict
incompatible uses, and develop agreements with
municipalities. The suspension is not intended to identify
and protect municipal watersheds or adjust land management
plans. The identification and protection of municipal
watersheds is most appropriately analyzed in forest plans
and these analyses were done for inventoried watersheds in
forest planning. Additionally, in many cases, municipal
watersheds are already roaded to provide access for
management to protect water quality and other resource needs
associated with these special areas. Reconstruction of these
roads may be required to maintain water suitable for
municipal water supplies.
Apply suspensions to sensitive wildlife areas. Forest
Service Manual 2670 provides direction pursuant to
implementing section 7 of the Endangered Species Act (ESA).
Forest Service policy is to implement objectives and actions
to contribute to the recovery of listed species. Direction
also is provided regarding consultation under ESA to ensure
that Forest Service actions do not jeopardize the existence
of any species or destroy or adversely modify critical
species habitat designated under ESA. Forest Service policy
is to ensure that species do not become threatened or
endangered because of Forest Service action and to maintain
viable populations as defined in National Forest Management
Act (NFMA) regulations. The Forest Service prepares
biological evaluations to determine an action's potential
effect on sensitive species. Regional Foresters have the
responsibility to identify sensitive species. An interim
approach to protecting selected 1,000-acre areas would be
inconsistent with, and not as biologically effective as, the
continued emphasis on developing conservation strategies,
assessments, and agreements. Developing conservation
strategies, assessments, and agreements, on-going in every
Forest Service region, contributes to species viability and
mitigates the need to list species as threatened or
endangered under ESA.
Apply proposed temporary suspension retroactively to road
construction projects under contract. The Forest Service
honors contracts and permits and believes that resources are
best devoted to proactive policy development rather than
extended debate over existing contract modifications.
Environmental impacts from past activities will be addressed
in the comprehensive revision of the long-term
transportation policy.
Suspend all road construction on all NFS lands.
Although suspending all road construction would be
environmentally beneficial, such action would broadly extend
the geographic scope of the proposal. This proposal is to
preserve the resource options of unroaded areas from
potentially adverse effects associated with permanent and
temporary road construction and reconstruction while
adopting a revised road management policy.
Make proposed temporary suspension permanent or
indefinite. This action would extend the temporal scope
of the proposed temporary suspension, which is to provide a
safeguard while a long-term transportation system policy is
developed. The question of permanent suspension of road
construction is most appropriately left to the Agency's
long-term transportation system policy under development.
Exempt significant forest plan amendments. Only one
significant forest plan amendment was identified; the Winema
National Forest proposed forest plan amendment for the
Pelican Butte Ski Project scheduled for completion in fiscal
year 1999. This forest plan amendment is already exempt as a
part of the NWFP.
Environmental Consequences
The estimated road miles for permanent and temporary road
construction and reconstruction on all NFS lands (roaded and
unroaded) used in this EA are for purposes of this analysis
only. These estimates were not developed as a part of the
formal processes used for budget planning, site-specific
NEPA analysis, and on-the-ground project scheduling. They
represent a one-time survey of field units of all possible
road miles for an 18-month period. Adjustments have been
made to the field data based on road projects over the
3-year period reflected in the fiscal year 1999 Presidential
Budget.
The primary factor in estimating the effects of permanent
and temporary road construction and reconstruction is the
number of miles rather than the number of projects. Projects
vary considerably in size and type and have been referred to
in terms out outputs (e.g., volume of timber). The action
suspends roads not projects. A direct relationship exists
between permanent and temporary road construction and
reconstruction miles and resource effects.
Although the mileage estimates are the most accurate
information on permanent and temporary road construction and
reconstruction on all NFS lands, they are constantly
changing. Many of the estimated road miles will be altered
or abandoned during planning and site-specific NEPA
analysis, others will be delayed by appeals, litigation, and
needed environmental information, some will be completed,
and others will be added within the 18-month period. The
18-month period does not assume a start or end date. The
estimates cannot be used, with precision or certainty,
regarding effects on any specific national forest. The
effects are characterized at national, regional, and
sub-regional levels.
The estimates used in the EA should not be used to
calculate revenues lost as cited under the provisions of P.L.
105-174, Section 3006, 1998 Supplemental Appropriations and
Rescissions Act. When the final interim rule is published,
specific implementation direction will be established to
evaluate projects and determine the extent of the
compensation needed for lost revenue.
Certain types of projects, such as special use permits
and lands and minerals activities, are affected largely by
forces outside the Forest Service. Private parties may
propose new uses of NFS lands that are then considered by
the Forest Service. Under all alternatives, each road
project would be evaluated on a case-by-case basis to
determine whether the proposed temporary suspension applies
or if the project qualifies under an exemption. Table 4 and
Figure 1 show the permanent and temporary road construction
and reconstruction miles suspended, on NFS lands by natural
resource purpose and alternative, during the proposed
temporary suspension.
Table 4. Permanent and
temporary road construction and reconstruction miles
suspended on unroaded National Forest System lands by
primary road purpose during the proposed temporary
suspension for alternatives 2 through 5.1

1
Numbers may not total due
to rounding. Where conflicts occur due to rounding, original
data was used.
Assumptions
The following assumptions were made to estimate the
effects of the alternatives.
Duration of effects. Although the proposed temporary
suspension would last for a maximum of 18 months, some
effects may last longer. Specifically, social and economic
effects from suspended projects would occur over periods
that may exceed the 18-month period. For example, timber
from a suspended timber sale is assumed not to be harvested
in 1 year, rather the volume is dispersed over 3 years (but
the suspension period remains 18-months). This accurately
reflects how timber sales usually progress when providing
market and extends the economic effects over multiple years
rather than one. When such assumptions are used in the
analysis, they are discussed.
Projects may proceed without road construction. The
analysis of effects assumes that planned projects involving
road construction or reconstruction in unroaded areas of NFS
lands would be suspended. However, once the final interim
rule is effective, each unit will be required to evaluate
all potentially affected projects (under the provisions of
P.L. 105-174, Section 3006, 1998 Supplemental Appropriations
and Rescissions Act) to determine if it can be implemented
without the road work. For example, oil drilling in a
unroaded area could be accomplished by transporting
equipment by helicopter. In addition, some projects may
involve unroaded areas of NFS lands subject to suspension
and roaded areas not subject to suspension; this is common
for timber sales that involve relatively large areas. In
these situations, suspending the unroaded portion may
require suspending the entire project if the roaded portion
cannot proceed on its own. For discussion of timber sales in
this analysis, a range of miles is provided with the lower
value being the portion of the project within the unroaded
area subject to suspension and the higher value being the
entire project. Once the final interim rule is effective,
each unit will evaluate any split projects to determine if
the portion that is unaffected by the suspension can
proceed.
Road reconstruction in unroaded areas of NFS lands.
Depending on the road type, it is possible for road
reconstruction to occur during the proposed temporary
suspension. For example, when an unclassified road
(Glossary) exists in an unroaded area or in a roadless area
(Glossary) reconstruction could proceed. However, usually
road reconstruction is for unclassified roads that require
betterment, restoration, or realignment to alleviate a
resource concern.
Road Miles Suspended
Under current management, permanent and temporary road
construction and reconstruction is estimated to be 8,948
miles on all NFS lands and 534 miles in unroaded areas of
NFS lands during the 18-month suspension period. Figure 2
shows the permanent and temporary road construction and
reconstruction miles by Forest Service region that would be
suspended under alternatives 2 through 6 on unroaded NFS
lands. Figure 3 compares, by alternative, the permanent and
temporary road construction and reconstruction miles that
are estimated and that would be suspended on all NFS lands
during the proposed temporary suspension. Figure 4 compares,
by alternative, the permanent and temporary road
construction and reconstruction miles that would be
suspended on unroaded NFS lands during the proposed
temporary suspension.
The following discussion addresses estimated permanent
and temporary road construction and reconstruction miles in
unroaded areas of NFS lands. Estimates are for an 18-month
period and are for miles constructed or reconstructed, not
acreage affected by projects. All existing contracts,
permits, other instruments of authorization, and MOUs
existing as of the effective date of the final interim rule
would be exempt from the proposed temporary suspension. In
addition, activities often associated with roads that can be
accomplished without road construction (e.g., timber harvest
by helicopter or from existing roads) would be unaffected.
Routine maintenance of existing roads would be unaffected by
all alternatives.
Figure 1.
Comparison of permanent and temporary construction and
reconstruction of forest development road miles by natural
resource purpose that would be suspended under alternatives
2 through 6.

Figure 2. Miles
of permanent and temporary road construction and
reconstruction by Forest Service region that would be
suspended under alternatives 2 through 6.

Figure 3.
Comparison of the alternatives of the reconstruction,
construction, and temporary construction road miles that
would be suspended during the proposed temporary suspension.

Figure 4.
Comparison by alternative of the the forest development road
miles that would be suspended during the proposed temporary
suspension.

Figure 5.
Baseline miles of permanent and temporary road construction
and reconstruction by natural resource purpose.

Alternative 1 - Current
management. Since
there is no suspension under this alternative, it represents
the estimated permanent and temporary road construction and
reconstruction miles for the 18-month period based on forest
plans, expected budgets, and estimated likelihood of project
implementation. The estimated miles of permanent and
temporary road construction and reconstruction is 8,948
miles on all NFS lands and 534 miles in unroaded areas of
NFS lands.
Alternative 2 - RARE II with exemptions. This
alternative would temporarily suspend an estimated 207 miles
of construction and reconstruction in unroaded portions of
inventoried RARE II areas and areas inventoried in forest
plans that lie one-quarter mile of more beyond any
classified road. This involves an estimated 72 miles (35% of
the total miles for alternative 2) of road construction, 69
miles (33% of the total miles for alternative 2) of
reconstruction, and 66 miles (32% of the total miles for
alternative 2) of temporary road construction. The most
miles affected under this alternative would be in Region 8
(37% of the total miles for alternative 2), Region 4 (20% of
the total miles for alternative 2), and Region 1 (18% of the
total miles for alternative 2). The majority of estimated
permanent and temporary road construction and reconstruction
miles temporarily suspended under this alternative are for
forest management (timber) purposes.
Alternative 3 - Proposed action. This alternative
would temporarily suspend an estimated 243 miles of
permanent and temporary road construction and
reconstruction. This involves an estimated 78 miles (32% of
the total miles for alternative 3) of road construction, 75
miles (31% of the total miles for alternative 3) of
reconstruction, and 90 miles (37% of the total miles for
alternative 3) of temporary road construction. The most
miles affected under this alternative would be in Region 8
(31% of the total miles for alternative 3), Region 4 (17% of
the total miles for alternative 3), and Region 1 (16% of the
total miles for alternative 3). The majority of permanent
and temporary road construction and reconstruction miles
temporarily suspended under this alternative are for forest
management (timber) purposes.
Alternative 4 - Broadest safeguards. This alternative
would temporarily suspend an estimated 461 miles permanent
and temporary road construction and reconstruction. This
involves an estimated 213 miles (46% of the total miles for
alternative 4) of road construction, 92 miles (20% of the
total miles for alternative 4) of reconstruction, and 155
miles (34% of the total miles for alternative 4) of
temporary road construction. The most miles affected under
this alternative would be in Region 10 (35% of the total
miles for alternative 4), Region 8 (20% of the total miles
for alternative 4), and Region 4 (10% of the total miles for
alternative). The majority of estimated permanent and
temporary road construction and reconstruction miles
temporarily suspended under this alternative are for forest
management (timber) purposes.
Alternative 5 - RARE II without exemptions. This
alternative would temporarily suspend an estimated 401 miles
of permanent and temporary road construction and
reconstruction. This involves an estimated 201 miles (50% of
the total miles for alternative 5) of road construction, 75
miles (19% of the total miles for alternative 5) of
reconstruction, and 125 miles (31% of the total miles for
alternative 5) of temporary road construction. The most
miles affected under this alternative would be in Region 10
(40% of the total miles for alternative 5), Region 8 (23% of
the total miles for alternative 5), and Region 4 (10% of the
total miles for alternative 5). The majority of estimated
permanent and temporary road construction and reconstruction
miles temporarily suspended under this alternative are for
forest management (timber) purposes.
Alternative 6 - Preferred alternative. This
alternative would temporarily suspend an estimated 262 miles
of permanent and temporary road construction and
reconstruction. This involves an estimated 81 miles (31% of
the total miles for alternative 6) of road construction, 78
miles (30% of the total miles for alternative 6) of
reconstruction, and 102 miles (39% of the total miles for
alternative 6) of temporary road construction. The most
miles affected under this alternative would be in Region 8
(33% of the total miles for alternative 6), Region 4 (17% of
the total miles for alternative 6) and Region 1 (16% of the
total miles for alternative 6). The majority of estimated
permanent and temporary road construction and reconstruction
miles temporarily suspended under this alternative are for
forest management (timber) purposes.
Figure 5 shows the permanent and temporary road
construction and reconstruction miles that are estimated
under alternative 1 on all NFS lands. Figure 1z shows
permanent and temporary road construction and reconstruction
miles on unroaded NFS lands suspended under alternatives 2
through 6 by natural resource purpose.
Access and Public Safety
Public safety would be unaffected under any of the
alternatives. For new general access the effect of the
proposed temporary suspension would be negligible under all
alternatives. In addition, the differences between
alternatives are minimal.
Access is the opportunity to enter NFS lands for personal
and reasonable use of other lands and rights within the NFS
lands. The National Forest Transportation System,
approximately 373,000 miles of roads, includes 23% arterial
or collector roads, that serve all users and 57% local
roads, that are typically passable by high-clearance
vehicles. Access to the remaining 20% of these roads is
restricted by gates or other methods. An estimated average
of 1.7 million vehicles per day use the National Forest
Transportation System. Additionally, 15,000 commercial
vehicles associated with timber harvesting and the
development of other resources use the system daily. An
estimated 9,000 Forest Service vehicles drive system roads
daily to accomplish a variety of administrative tasks such
as fire suppression, contract administration, resource
projects, and law enforcement. Where the primary purpose
identified for road construction and reconstruction is for
access, the action will probably involve repair of NFS roads
damaged by flooding in 1997 and 1998.
Permanent and temporary road construction and
reconstruction on all NFS lands for general access during
the proposed temporary suspension is an estimated 859 miles
of road reconstruction, 19 miles of road construction, and
less than a mile of temporary road construction. Permanent
and temporary road construction and reconstruction miles on
all NFS lands for public safety during the proposed
temporary suspension is an estimated 36 miles of road
reconstruction, 7 miles of road construction, and less than
a mile of temporary road construction (table 5).
The effects of the alternatives on general access range
from no impact under alternative 1 to less than 1% of access
miles suspended under alternative 4 on all NFS lands during
the 18-month temporary suspension period. An exemption
applies to public safety under all alternatives, therefore,
it would be unaffected.
Table 5. Summary of the
planned general access and access for public safety programs
to National Forest System land during the proposed temporary
suspension of road construction and reconstruction,
including the construction of temporary roads, in most
unroaded areas of the National Forest System.
| |
Reconstruction
a |
Construction
a |
Temporary
construction a |
| General
access |
859 |
19 |
<1 |
| Public
safety |
36 |
7 |
<1 |
| Total |
895 |
26 |
1 |
a Values
are in miles
Alternative 1 - Current management. Under this
alternative, permanent and temporary road construction and
reconstruction for the primary purpose of general access is
estimated to be 7 miles in unroaded areas of NFS lands. No
miles were identified specifically for the primary purpose
of public safety in unroaded areas during the 18-month
suspension period. General access provided by permanent and
temporary road construction and reconstruction in unroaded
areas of NFS lands would be unaffected under this
alternative.
Alternatives 2, 3, and 6. Less than 1% of the
estimated road construction and reconstruction identified
for the primary purpose of general access would be suspended
under these alternatives on unroaded areas of NFS during the
18-month suspension period. No temporary road construction
would be suspended. There would be no effect on general
public safety due to the exemption applied under all
alternatives.
Alternative 4 and 5. Less than 1% of the estimated
road construction and reconstruction identified for the
primary purpose of general access would be suspended under
these alternatives on unroaded areas of NFS during the
18-month suspension period. No temporary road construction
would be suspended. These alternatives differ from
alternatives 2, 3, and 6 by suspending of 1 additional mile
of road reconstruction. The effect of the proposed temporary
suspension on general access would be negligible at Forest
Service regional and national levels. There would be no
effect on general public safety due to the exemption applied
under all alternatives.
Fire, Insects, and Disease
Approximately 40 million acres of all NFS lands are at
abnormally high risk of catastrophic fire, disease, and
insect outbreaks. In 1997, the Forest Service treated
286,000 acres by commercial thinning and salvage using
timber sales. Under current management, many acres will
likely burn or be subject to insect attack before they can
be treated. The Forest Service plans to treat approximately
514,000 acres in 1998 and 1999. A maximum of 15,000 acres
have been estimated for treatment in unroaded areas of NFS
lands during the 18-month suspension period, which is 3% of
the need on all NFS lands. There is a greater need for
treatment than can be accomplished across NFS lands each
year. Any reduction of forest health projects in unroaded
areas of NFS lands would likely be balanced by increased
forest health projects in roaded areas.
Some of the projects that would be affected by the
proposed temporary suspension are intended to improve forest
health. These include thinning, salvage, or regeneration to
restore forests affected by fire suppression to less fire
prone conditions. Without such treatments, the risk of
catastrophic wildfire and local insect and disease epidemics
could be high for some areas.
Roads provide access for fire suppression forces and
equipment and for human-caused fire. Road development often
increases the risk of human-caused fires by increasing
exposure of fuels to human activities. Human-caused fires
occur frequently in areas served by roads; however, these
fires are sometimes more easily suppressed because of the
road access. With an existing road system estimated at
373,000 miles, a variation of a few hundred miles would not
have an appreciable effect on initial suppression
effectiveness due to alternative firefighting strategies. In
addition, because prescribed burns (fires ignited by
management actions to meet specific objectives) rarely
involve road construction or reconstruction, they would be
unaffected by the proposed temporary suspension. Initial
suppression strategies for fire suppression depend on the
presence or absence of roads. The use of aerially delivered
fire fighters into unroaded areas of NFS lands is often as
effective as conventional fire truck suppression in roaded
areas.
Federal fire policy recognizes the benefits of
landscape-scale wildland fire including prescribed fire.
Prescribed fire is independent of roads as alternatives
exist that are often more effective and less costly; for
example, natural features and short-term fire break
construction. The marginal benefit of new road construction
and its ancillary increased human exposure is insignificant
when viewed in light of alternative suppression strategies.
In 1997, more than 1 million acres of hazardous fuels
were treated. In 1998, 1.2 million acres will be treated.
This effort is estimated to increase to an average of 3
million acres per year on a continuous, rotational basis.
All these acres can be treated without roads. The physical
conditions that predispose forests to catastrophic fire,
such as overly dense stocking, large continuous amounts of
volatile fuels, and severe fire weather, greatly exceed the
impact of the roads system.
At the local level, the short-term risk of insect
epidemics is highest in the South, while the risk of
catastrophic fire is highest in the Intermountain West and
California. Conifer forests of Idaho, Colorado, eastern
Oregon, and the Sierra Nevadas often juxtapose severe fire
risk with residential development in the wildland/urban
interface. Across the Coastal Plain and Piedmont, southern
pine beetle populations are building to epidemic levels, but
the Talladega National Forest in Alabama is particularly
affected by the southern pine beetle.
Alternative 1 - Current management. Under this
alternative, temporary road construction for fire
suppression is estimated to be 6 miles in unroaded areas of
NFS lands during 18-month suspension period. There are no
permanent road construction and reconstruction miles
estimated because forest health treatments in unroaded areas
of NFS lands may be offset by treating roaded areas. The
proposed temporary suspension would not appreciably affect
the health of NFS forests from a national perspective.
Alternative 2 through 6. Homes are being built in
wildlands. This is called the wildland/urban interface.
Priorities for forest health and fire treatments tend to be
in interface areas, which tend to be more roaded.
Nationwide, there are more opportunities for forest health
and fire treatment than there are funds available. The
suspension of permanent and temporary construction and
reconstruction on forest health and fire treatment in
unroaded areas by alternatives 2 through 6 would likely
cause the work to be accomplished in unroaded areas to shift
to roaded areas. There would be a slight disruption in the
forest health and fire treatment programs as work is
redirected from unroaded areas to roaded areas.
Where fuel loading is high under alternatives 2 through
5, in unroaded areas of NFS lands scheduled for salvage
logging or fuel treatment, suspension of permanent and
temporary road construction and reconstruction for these
projects could increase the risk of catastrophic wildfire in
some areas in the absence of alternative protection
strategies. Prescribed burning rarely involves road
construction or reconstruction. Local units have fire
suppression strategies and technology that provide
appropriate and timely protection for unroaded, high-risk
areas allowing a small increment of increased risk.
Therefore, there are protection strategies available that
minimize the risks.
Fire risk in the Intermountain West and in the increased
insect risk in the Coastal Plain, Piedmont and Alabama along
with localized impacts are mitigated under an alternative 6
exemption in unroaded areas within NFS where there is a need
to address an imminent threat of flood, fire, or other
catastrophic event that, without intervention would cause
the loss of life or property.
The risk of untreated beetle activity is also increased
where there is spread to adjoining private land resulting in
loss of valuable timber, wildlife habitat, and forest cover.
The FS conducts insect and disease surveys throughout the
country. By using the insect and disease survey under the
preferred alternative exemption to address an imminent
threat of flood, fire, or other catastrophic event; specific
areas could be identified for treatment that without
intervention would cause the loss of life or property.
Forest Management (Timber)
Timber sales are used to achieve vegetation management
objectives. These objectives include providing a sustainable
yield of forest products to meet the nation's demands, and
restoring, improving, and maintaining forest ecosystem
health. Timber sales are often used as a least-cost method
to manage vegetation for improving wildlife habitats,
reducing fuels that may increase fire risk, recovering value
from natural disasters, combating insect and disease
infestations, and improving tree growth. Table 6 shows the
national trends in the NFS timber program.
Roads are generally required for timber harvest. Some
timber sales can be harvested using helicopters or cable-yarding
systems from existing roads. Use of these methods depends on
the value of the timber being removed, the terrain, and the
distance to an existing road. Each timber sale contract
specifies the yarding method and any permanent and temporary
road construction and reconstruction required. Timber
purchasers may be required to complete needed road
reconstruction to ensure public safety and to protect the
environment from logging traffic. Roads that the Forest
Service has determined are needed for future multiple-use
management are constructed to meet road specifications and
retained for future use after the timber sale. Temporary
roads are constructed only for the duration of the timber
sale. Even though a sale may require helicopter logging,
some road reconstruction may be needed and temporary road
construction may be required.
Public comments about the timber sale program focused on
delays in the amount of timber offered for sale and the
resulting effect on jobs, income, payments-to-states, timber
supply, imports, and other economic considerations
(Economics and Appendix D).
United States wood consumption would be unaffected by the
proposed temporary suspension. The reduction in timber sale
offerings because of the proposed temporary suspension would
eventually result in a minor reduction in national forest
timber harvest. The effect of this reduction would depend on
the local relationship between national forest timber sales
and local supply and demand. There would be ample
opportunity to substitute timber from other ownerships to
replace most of the reduction in national forest timber
sales in the eastern United States. In the West,
substitution opportunity is limited, any volume that could
not be substituted from other United States ownerships could
probably be met by Canadian imports. The reduction in
national forest timber volume sold from more than 11 billion
board feet in 1987 to 3.4 billion board feet in 1996 was
offset by an increase in Canadian imports and private-land
harvesting. Since 1991, softwood lumber imports from Canada
have increased from 10.5 billion board feet to 17.8 billion
board feet, and United States softwood consumption of
Canadian imports has increased from 27% to 36%. The impact
is small without a marked change in total number of imports
from Canada; therefore, the effect to the Canadian
environment is insignificant.
The Forest Service estimates the amount of timber to be
offered for sale at a given budget level each fiscal year. A
timber sale generally requires several years of preparation
from identification of the need until final sale offering.
During this time, the sale must meet all legal requirements
including those mandated by NFMA and NEPA.
Table 6. National trends in
the National Forest System timber program offered.
| |
Volume b |
Reconstruction c |
Construction c |
| FY 1997a |
4,001 |
3,285 |
392 |
| FY 1998d |
3,813 |
3,203 |
510 |
| FY 1999d |
3,439 |
2,957 |
403 |
a actual
b Values in million board feet.
c Values in miles.
d estimate
The timber volume affected by
the various alternatives is based on the annual estimate of
capability, considering budget constraints, and on the stage
of the timber sale preparation process. Each national forest
has an estimate of the allowable sale quantity that
establishes a ceiling on the timber harvest for that forest.
However, forests frequently do not achieve the allowable
sale quantity because of budget limitations and conditions
that have occurred since their allowable sale quantities
were determined. In addition, estimated volumes are based on
timber sales currently in the planning phase; therefore,
there is no guarantee that the estimated volume for sale
would be the actual volume for sale. Appeals and litigation
can also cause delays in timber sale offerings. These
factors were considered when estimating the potential
suspension in timber volume offered for sale under the
various alternatives. The volume estimates are based on
estimated sales for an 18-month period, but these sales are
not actually scheduled.
Modifications made to individual timber sales after the
effective date of final interim rule would minimize effects
on timber output. These modifications may include dropping
the portion of a sale affected by the suspension, changing
to a harvest method that does not require roads, or
substituting volume from a sale estimated for future years.
There could also be an additional decrease in volume if
suspending a portion of the sale makes the entire sale
infeasible. For example, for a timber sale that encompasses
a relatively large area, suspending the unroaded portion may
force suspension of the entire project. After the effective
date of the final interim rule, each unit will evaluate any
possible split projects to determine if the volume outside
the unroaded area can proceed.
The timber sale program used for analysis is based on
fiscal year 1998 appropriation and fiscal year 1999
Presidential Budget. The effect on the timber sale program
is directly related to the number of miles requiring road
construction or reconstruction that would be suspended by
the proposed temporary suspension. The volume of timber sold
is generally similar to volume offered for sale; however,
there is often a decrease in volume sold because there were
no sale bids. The average percentage of volume that was
offered for sale but was not sold during fiscal years 1995
through 1997 was 7.5%.
The volume of timber harvested follows the trend of
volume sold but is further delayed. Most of the timber
harvested in a particular year is from timber sales that
were sold in previous years. Usually 2 to 3 years are
required from the time the timber is sold until all the
timber is harvested. The volume harvested is based on
inventory needs and market conditions. Harvest volume
mitigates the peaks and valleys in the timber market. The
effect of the proposed temporary suspension could be felt in
the harvest market in 1998 and continue into 2004, depending
on the offering of the suspended sales. Harvest volume is
used to project jobs, revenues, and payments-to-states under
current law. Provisions of the 1998 Supplemental
Appropriations Rescission Act (PL 105-174) will, to some
extent, compensate for shortfalls in payments-to-states from
revenues generated on NFS lands.
A range of timber volumes offered for sale was developed
as the basis for estimating impacts (table 7). The low range
is the volume in an unroaded area where permanent and
temporary road construction and reconstruction would be
suspended. The high range is the volume in an unroaded area
where permanent and temporary road construction and
reconstruction would be suspended plus any volume that is
part of the suspended timber sale but is not in the unroaded
area. This assumes that the volume not in the unroaded area
is not viable as a separate sale. Both the low and high
estimates were reduced to reflect the difference between the
volume estimated for sale and the actual volume offered for
sale. Estimated sale volumes are usually reduced during the
sale design and preparation process due to site-specific
volume estimates, mitigation measures, appeals, and
litigation. Appendix D shows the affected volume and
resulting effects on jobs, revenues, and payments-to-states
by region.
Table 7. Low and high range
of timber volumes offered for sale, by alternative, that
would be suspended during the proposed temporary suspension
of permanent and temporary road construction and
reconstruction in unroaded areas of the National Forest
System land.

a Values in million board feet.
b Values in miles.
Alternative 1 - Current
management. Under
this alternative, 375 MMBF of timber would be offered for
sale requiring 46 miles of reconstruction, 183 miles of
construction, and 136 miles of temporary road construction
in unroaded areas of NFS lands during the 18-month
suspension period. This alternative represents a timber sale
program for a typical 18-month period. Based on the
estimated fiscal year 1998 timber sale program and the
fiscal year 1999 budget request, 5.44 billion board feet of
timber would be offered for sale during a typical 18-month
period. Approximately 3,654 miles of road reconstruction,
649 miles of road construction, and 1,652 miles of temporary
road construction would be required to harvest this volume
on all NFS lands during the 18-month suspension period.
Alternative 2 - RARE II with exemptions. The proposed
temporary suspension could affect the sale offering of
approximately 124 MMBF by suspending 56 miles of road
construction, 37 miles of road reconstruction, and 57 miles
of temporary road construction for vegetation management
purposes. An additional sale offering of approximately 57
MMBF of timber could be suspended because, although not
directly affected by the proposed temporary suspension, it
would be associated with a suspended volume. The actual
amount of volume affected would depend on site-specific
analysis of each affected timber sale to determine if the
portion of the sale not directly affected by the suspension
could proceed if the unroaded portion was suspended. About
78% of the volume affected under this alternative occurs in
Regions 1, 4, and 8, which have more timber sales proposed
in RARE II areas than other regions.
Alternative 3 - Proposed action. The proposed
temporary suspension could affect the sale offering of
approximately 159 MMBF by suspending 58 miles of road
construction, 41 miles of road reconstruction, and 81 miles
of temporary road construction for vegetation management
purposes. An additional sale offering of approximately 97
MMBF of timber could be suspended because, although not
directly affected by the proposed temporary suspension, it
would be associated with a suspended volume. The actual
amount of volume affected would depend on site-specific
analysis of each affected timber sale to determine if the
portion of the sale not directly affected by the suspension
could proceed if the unroaded portion was suspended. The
increase in volume, as compared to alternative 2, results
from inclusion of unroaded areas of NFS lands adjacent to
existing Wilderness Areas, rivers classified as Wild, and
areas adjacent to unroaded areas on other Federal
ownerships. Regions 5 and 9 account for 89% of the increase
between alternatives 2 and 3. There would be little change
in the volume affected between alternative 3 and alternative
2 in Regions 1, 4, and 8. These 3 regions account for 62% of
the total volume affected by alternative 3.
Alternative 4 - Broadest safeguards. The proposed
temporary suspension could affect the sale offering of
approximately 327 MMBF by suspending 188 miles of road
construction, 48 miles of road reconstruction, and 142 miles
of temporary road construction for vegetation management
purposes. An additional sale offering of approximately 237
MMBF of timber could be suspended because, although not
directly affected by the proposed temporary suspension, it
would be associated with a suspended volume. The actual
amount of volume affected would depend on site-specific
analysis of each affected timber sale to determine if the
portion of the sale not directly affected by the suspension
could proceed if the unroaded portion was suspended.
Eliminating the exemptions for revised forest plans and the
NWFP had the largest impact on the increase in volume
subject to suspension under alternative 4 as compared to
alternatives 2 and 3. Inclusion of the Tongass National
Forest accounted for a 61% of the increase, while the NWFP
accounted for a 20% of the increase in the volume subject to
suspension as compared to alternative 3.
Alternative 5 - RARE II without exemptions. The
proposed temporary suspension could affect the sale offering
of approximately 256 MMBF by suspending 178 miles of road
construction, 39 miles of road reconstruction, and 112 miles
of temporary roads construction for vegetation management
purposes. An additional sale offering of approximately 204
MMBF of timber could be suspended because, although not
directly affected by the proposed temporary suspension, it
would be associated with a suspended volume. The actual
amount of volume affected would depend on site-specific
analysis of each affected timber sale to determine if the
portion of the sale not directly affected by the suspension
could proceed if the unroaded portion was suspended. This
alternative is similar to alternative 2 in that it would
suspend RARE II areas but differs from alternative 2 by
eliminating the exemptions for revised forest plans and the
NWFP. There is an increase of approximately 92% in volume
affected by the suspension under alternative 5 as compared
to alternative 2 because of the Tongass National Forest and
the NWFP inclusion.
Alternative 6 - Preferred alternative. The proposed
temporary suspension could affect the sale offering of
approximately 170 MMBF by suspending 64 miles of road
construction, 43 miles of road reconstruction, and 89 miles
of temporary road construction for vegetation management
purposes. An additional sale offering of approximately 90
MMBF of timber could be suspended because, although not
directly affected by the proposed temporary suspension, it
would be associated with a suspended volume. The actual
amount of volume affected would depend on site-specific
analysis of each affected timber sale to determine if the
portion of the sale not directly affected by the suspension
could proceed if the unroaded portion was suspended.
Alternative 6 and alternative 3 are similar in their effect
on volume offered for sale. The increase in volume suspended
under this alternative, as compared to alternative 3, is
because of inclusion of unroaded areas of 1,000 or more
acres adjacent to Forest Service RARE II areas. Regions 1,
4, and 8 account for 61% of the volume affected by the
suspension, which is similar to alternative 3.
Old Growth. A subset of public comments regarding the
proposed temporary suspension focused on old-growth forests.
Some respondents believed that the suspension would result
in protection of old-growth forests from road construction
and logging activities, while others were concerned over the
risk of insect infestations and wildfires in these forests.
While data is unavailable regarding the amount of road
activity in old-growth forests that would be suspended, it
is assumed that road construction associated with logging
activities in some old-growth forests would be suspended.
Forest managers may examine local road systems in the
context of old-growth management objectives through
application of a long-term transportation system policy.
This integrated approach would help to ensure that future
road systems are consistent with old-growth management
objectives established in forest plans. Under alternatives 2
through 6, there is a small increase in the possibility that
some old-growth forests in unroaded areas of NFS lands would
be protected during the 18-month suspension period.
Alternative 4 provides the most protection for old-growth
forests, while alternative 2 provides the least.
Special Forest Products. Special forest products
include house logs, posts, poles, Christmas trees,
mushrooms, beargrass, pinyon nuts, berries, and ferns. There
is a continuing public demand for these products for cottage
industries and personal use. Roads are not constructed nor
reconstructed solely for the removal of special forest
products. The proposed temporary suspension would not affect
the removal of special forest products. A minimal decrease
in general new access as a result of the suspension may
affect potential new opportunities to access special forest
products. Current access is adequate to meet current demand
for special forest products.
<<
Previous Section 1 - 2
- 3 - 4
- 5 Next
Section >>
|